Marshall to Vesta

Traffic impacts

Current traffic impacts

  • Project is being constructed under traffic utilizing a flagger and pilot car.

Project updates

  • Cold in place recycle (CIR) operations are complete.
  • Hwy 67 (Echo) is expected to be complete the first week of November. Shoulder work, rumble strip installation and striping work remain.
  • Hwy 19 (Marshall to Vesta) - working on paving, shoulders and installation of rumble strips. Hoping to have work complete by the first week of November. Seal coat, fog seal and final striping will be completed in spring of 2018.

 

About this project

Summary of work

  • Preservation project
  • 4.5" CIR with 1.5" bituminous overlay and seal coat
  • Cold-in place recycle (CIR): cold-in place recycle consists of milling up in place bituminous pavement, crushing the materials, adding oil, remixing it, followed by re-laying the materials with a paver and compacting it.
  • A CIR is cost effective and environmentally friendly because it recycles existing materials and reduces trucking by not having to remove the material from the roadways while limiting the amount of new materials that need to be hauled in.

Contractor

  • Duininck Inc.