HIGHWAY 7 CONSTRUCTION SCHEDULE UPDATE


Willmar, Minn. -

The Minnesota Department of Transportation, Hutchinson office, announced today that concrete paving on Trunk Highway 7 east of Hutchinson will be delayed for two weeks due to the concrete paver being moved to another project. According to Mn/DOT officials, construction will continue and concrete paving will resume, weather permitting, on Monday, October 22.


The following is a construction update:

Concrete paving of both lanes, excluding shoulders, have been completed between 5th Avenue in Hutchinson to near the Bohemian Cemetery just three miles west of Silver Lake. Aggregate placement on the remaining three miles, including Silver Lake, will continue in preparation of concrete paving.

Mn/DOT will continue to provide local access and begin to open completed portions of the highway to local traffic only. Concrete cure time, placement of aggregate shoulders, striping and signing will need to be completed before opening any section of the highway.

Re-shaping of shoulders, grading of road ditches and spreading of topsoil will continue.


Weather permitting, the detour will be removed by mid-November.

See ORANGE.

We’re in the WORK ZONE Together


  District 8 - Willmar/Marshall/Hutchinson
2505 Transportation Road
P.O. Box 768
Willmar, MN 56201
Tel: (320) 231-5195
Tel: (800) 657-3792
Contact:
Sandy East
Public Affairs Coordinator
320-214-3773 or
Gene Setrum
Project Supervisor
320-234-4200