Willmar,
Minn. - Weather permitting, the bituminous overlay and bridge replacement
project on Highway 75 between junction Highway 40 at Madison to
junction Highway 7 near Odessa will begin the week of May 14.
It will be necessary
to detour traffic during the project. According to Jim Christensen,
project supervisor at the Minnesota Department of Transportation,
traffic will be detoured via Highway s 40, 119 and 7 (see
map). The detour route adds approximately 15 miles.
The prime contractor
for the $2,200,000 improvement project is Mark Sand and Gravel,
Fergus Falls, Minn. The project is expected to be complete in mid-October.
For statewide
up-to-date road condition information, motorists can go to Mn/DOT's
Web site at www.dot.state.mn.us and click on road conditions or
by calling 800-542-0220. Local recorded road condition information
may be obtained by calling 320-235-9230 (Willmar and Hutchinson
area) or 507- 537-6387 (Marshall area).
See
Orange.
we're in the WORK ZONE together