News Release

April 10, 2000


 

Willmar - Marshall - Hutchinson - 2000 Improvement Projects

View the District 8 project map.

Projects located in the Willmar Region

Contact: Jeff Vlaminck, Willmar Region Engineer
320-214-3718 or 1-800-657-3792
  1. Trunk Highway 40 west of Willmar
  2. Description: Widen and pave shoulders between junction T.H. 12 and County Road 47. Bituminous overlay between the Chippewa/Kandiyohi county line to County Road 47.

    Traffic Impact: Minor traffic delays. Flag personnel present.
    Project Dates: May to June
    Cost: $400,000

  3. Trunk Highway 12 in Willmar (downtown bypass)
  4. Description: Resurface roadway between 7th Street and Dolson Street, City to replace utilities.

    Traffic Impact: Traffic will be detoured.
    Project Dates: July to mid-September
    Cost: $418,000

  5. Trunk Highway 12 and County Road 5 west of Willmar
  6. Description: Construct left turn lane and signalization.

    Traffic Impact: Minor traffic delays.
    Project Dates: Mid-May to mid-June
    Cost: $135,000

  7. Trunk Highway 23 between Willmar and Clara City
  8. Description: Overlay and replacement of three bridges between junction County Road 5 and T.H. 7.

    Traffic Impact: Traffic will be detoured.
    Project Dates: May to September
    Cost: $4,170,000

  9. Trunk Highway 212 between Granite Falls and Montevideo
  10. Description: Mill and overlay with culvert replacements between junction T.H. 59 in Montevideo and Granite Falls.

    Traffic Impact: Traffic will be detoured.
    Project Dates: May to mid-September
    Cost: $2,439,000

  11. Trunk Highway 67 at Hazel Creek southeast of Granite Falls
  12. Description: Bridge replacement at Hazel Creek.

    Traffic Impact: Traffic will be detoured.
    Project Dates: May to mid-September
    Cost: $488,000

    Projects located in the Marshall Region

    Contact: Jim Curran, Marshall Region Engineer

    507-537-6146 or 1-800-657-3748

  13. Trunk Highway 68 west of Canby
  14. Description: Bituminous overlay between South Dakota state line and 2 mile west of junction T.H. 75 at Canby.

    Traffic Impact: Minor traffic delays.
    Project Dates: June
    Cost: $840,000

  15. Trunk Highway 19 and 68 east of Marshall
  16. Description: Mill and overlay and the replacement of bridges from T.H. 23 at Marshall to County Road 5.

    Traffic Impact: Traffic will be detoured.
    Project Dates: End of April to July
    Cost: $3,000,000

  17. Trunk Highway 14 east of Balaton
  18. Description: Mill and overlay between west city limits of Balaton and junction T.H. 59.

    Traffic Impact: Traffic will be detoured
    Project Dates: June and July
    Cost: $1,300,000

  19. Trunk Highway 23 between Florence and Russell
  20. Description: Mill and overlay between junction T.H. 14 at Florence and junction T.H. 91 near Russell.

    Traffic Impact: Traffic will be detoured
    Project Dates: Mid-July through September
    Cost: $2,600,000

  21. Trunk Highway 30 between Lake Wilson and Slayton
  22. Description: Mill and overlay between Ravine Street in Lake Wilson and east junction T.H. 91. Bituminous overlay between east junction T.H. 91 and junction T.H. 267. Mill and overlay in Slayton between junction T.H. 267 and T.H. 59.

    Traffic Impact: Minor traffic delays
    Project Dates: August and September
    Cost: $1,040,000

  23. Trunk Highway 268 in Edgerton
  24. Description: Reconstruct highway, including curb, gutter and sewer in Edgerton.

    Traffic Impact: Minor traffic delays and temporary rerouting of traffic
    Project Dates: June to October
    Cost: $1,000,000

    Projects located in the Hutchinson Region

    Contact: Dave Johnston, Hutchinson Region Engineer

    320-234-4287 or 877-682-8249

  25. Trunk Highway 15 north of Dassel
  26. Description: Bituminous overlay, turn lanes and culvert extensions between Dassel and Kimball.

    Traffic Impact: Minor delays with flag personnel directing traffic.
    Project Dates: End of April to July
    Cost: $2,061,000

  27. Trunk Highway 7 at junction T.H. 25 near Watertown/Mayer
  28. Description: Turn lane construction at junction T.H. 25.

    Traffic Impact: Minor traffic delays
    Project Dates: Mid-May to mid-June
    Cost: $354,000

  29. Trunk Highway 212 between Hector and Glencoe
  30. Description: Bituminous overlay between junction T.H. 4 at Hector and west junction T.H. 22 southwest of Glencoe.

    Traffic Impact: Minor delays with flag personnel directing traffic.
    Project Dates: Mid-August to mid-September
    Cost: $1,500,000

  31. Trunk Highway 212 between Danube and Olivia

    Description: Mill and overlay between east limits of Danube and 2 mile east of the west junction T.H. 71 in Olivia.

Traffic Impact: Traffic will be detoured.
Project Dates: August through September
Cost: $986,000

See ORANGE.

We’re in the WORK ZONE Together


  District 8 - Willmar/Marshall/Hutchinson
2505 Transportation Road
P.O. Box 768
Willmar, MN 56201
Tel: 320/231-5195
Tel: 800/657-3792
Contact:
Sandy East
Public Affairs Coordinator
320/214-3773