Red Wing Bridge Project

Construction Activities

2017

  1. Treat soil conditions on the Wisconsin approach.
  2. Construct bridge piers.
  3. Construct temporary bridge over Hwy 61.
  4. Add traffic signal.
  5. Reconstruct Hwy 61.
  6. Construct button-hook ramp and cul-de-sac on E. 3rd St.

Traffic

2018

  1. Continue bridge construction.
  2. Construct new bridge over Hwy 61.
  3. Construct slip ramp and bridge at Bluff St

Traffic

2019

  1. Construct Hwy 63 in Wisconsin.
  2. Construct west side of 825th St.
  3. Continue bridge construction

Traffic

2020

  1. Construct 825th St. jug-handle and east side of 825th St.
  2. Remove existing river crossing.
  3. Remove temporary bridge of Hwy 61.
  4. Construct Hwy 61 under the new Hwy 63 overpass.
  5. Construct Hwy 61 median.

Traffic

825th Street Detour

MAY 2017 – LATE 2019: ALL TRAFFIC DETOURED

Use 825th St. north of The Woodshed to access Harbor Bar, Island Campground, and marinas.

2020: EASTBOUND TRAFFIC DETOURED (SINGLE DIRECTION ONLY)

825th St. eastbound traffic should use the access north of The Woodshed to get to Harbor Bar, Island Campground, and marinas.

Final Design

TRAFFIC