  • Closure of Exit 41 - Off Ramp - at Interstate 35 for northbound traffic using the Bridge Street ramp will occur this next week for approximately five days from Monday morning, June 22, at 6:00 a.m. through Friday morning, June 26, at 11:00 a.m. for removal and replacement of a large storm drainage pipe.
  • Currently, motorists will see single-lane, head-to-head traffic on I-35 in Owatonna as well as offramp and onramp closures for northbound traffic. Northbound traffic is crossed over into the southbound lanes of I-35 south of Bridge Street. Northbound traffic will continue in a single lane, while southbound uses the other lane. Northbound traffic will cross back over to two lanes north of Steele County Road 2.

About this project

Summary of work

  • Replace 4 bridges on I-35
  • Replace I-35 pavement from Hoffman Drive interchange to south of Lemond Road
  • Add auxiliary lanes between Hoffman Drive interchange and Bridge Street interchange
  • Safety improvements at Hoffman Drive SB on ramp to I-35.

Cost

    • $19.1 million