This project will seek to implement the vision for Highway 52 to develop a fully access-controlled freeway between I-90 and the I-494 ring. This project will remove the last two traffic signals on this route.
Location
- Cannon Falls
Schedule
- 2011 - Acquired funding & begin Final Design of Project
- Early 2013 - First Phase of Construction
Cost
- First Phase - $25,000,000.00
- Total Project - $32,000,000.00
Documents
Technical Memorandums
- Environmental Assessment and Worksheet
- Planning Goals, Objectives, and Framework
- Summary of Background Data and Conditions
- Project Purpose and Need Framework
- Alternative Development and Initial Screening
- Traffic Forecasting
- Negative Declaration, FONSI, and Findings Document