Hwy 27, Hwy 75

Wheaton area

Project information

Wheaton area 2018 road construction map
2018 Wheaton area detour map

In 2018, MnDOT will resurface Hwy 27 from just west of Co Rd 6 to the west end of Wheaton and Hwy 75 from Dumont to Wheaton.

Current traffic impacts

  • Hwy 27 closed between Co Rd 6 and Wheaton. Traffic detoured to County Roads 6 and 9.
  • As of September 11, Hwy 75 will be closed between Co Rd 6 and Wheaton. Traffic detoured to County Roads 6 and 9.
    • Access will be maintained for local traffic. All other traffic must detour.

Future projects in the Wheaton area

2019

  • Resurfacing and pedestrian accessibility improvements along Hwy 27 and Hwy 75 in the city of Wheaton (Cost Est. $1.2 M)

2020

  • Hwy 75 Mustinka River bridge replacement (Cost Est. $2.5 M)