Hwy 78 Resurfacing/Battle Lake Reconstruction

Hwy 210 in Battle Lake to Hwy 10 in Perham

Weekly Project Updates

If you'd like to receive the latest construction updates for this project by email, please click here to begin the sign up process.

Nov. 18

Thank you for your patience and understanding while work was underway this fall.

Work will end soon for the season, but some additional elements of the project--including the amenity zones in downtown Battle Lake--will be completed in the spring.

Weekly schedule

Work completed the week of Nov. 11:

  • Temporary striping
  • Rumble Strips
  • Misc. Cleanup

Work to be completed yet this fall:

  • Install railings near steps in downtown Battle Lake
  • Place sand in the amenity zone area in downtown Battle Lake for the winter
  • Additional cleanup

Work to be completed next spring:

  • Pour amenity zones
  • Pave rest areas
  • Final striping

Nov. 8

Hwy 78 between Battle Lake and Perham

Hwy 78 re-opened to traffic on Monday, Nov. 4, between Battle Lake and Ottertail.  Motorists may encounter intermittent lane closures between Battle Lake and Perham as crews complete work near the shoulders.

Weekly schedule

Work completed the week of Nov. 4:

  • All paving complete (Except for the rest areas)
  • Shouldering is complete
  • Striping has begun

Tentative schedule for the week of Nov. 11:

  • Gravelling near approaches
  • Rumble strips will be installed
  • Striping will continue
  • Mailbox supports will be installed

Major traffic impacts the week of Nov. 11:

  • Intermittent lane closures possible where crews are working

Nov. 4

Hwy 78 detour lifted

Crews have removed the detour on Hwy 78 between Battle Lake and Ottertail.

Please note, motorists may encounter intermittent lane closures between Battle Lake and Perham as crews complete work near the shoulders and rural approaches. In addition, crews will continue final concrete work and related projects within Battle Lake.

Final weekly project meeting to held this week

The final weekly public meeting will be held Wednesday, Nov. 6, at 10 a.m. at the Battle Lake City Hall, 108 East Main Street, Battle Lake, Minn. Representatives from the Minnesota Department of Transportation and Mark Sand and Gravel will be available to answer questions.

Nov. 1

Hwy 78 between Battle Lake and Perham

Crews continue to pave in the Battle Lake area. Weather permitting, Hwy 78 will re-open to through-traffic between Battle Lake and Ottertail (including within Battle Lake) by early next week.

Motorists may encounter intermittent lane closures between Battle Lake and Perham as crews complete work near the shoulders and rural approaches.

Weekly schedule

Work completed the week of Oct. 28:

  • Additional paving completed between Battle Lake and Ottertail
  • Paving (1st lift) within Battle Lake
  • Additional concrete curb and gutter (and sidewalks) poured in Battle Lake

Tentative schedule for the week of Nov. 4:

  • Complete paving in rural areas and within Battle Lake
  • Shouldering complete by the middle of the week
  • Concrete work (except for the amenity zone) complete by the middle of the week
  • Rumble Strips and temporary striping (for the winter) complete by the end of the week

Major traffic impacts the week of Nov. 4:

  • Pilot car operations for paving
  • Detour from Ottertail to Battle Lake (ending by early next week)
  • Battle Lake downtown road closure (ending by early next week)

Oct. 25

Hwy 78 between Battle Lake and Perham

Crews continue paving between Ottertail and Battle Lake, and they will begin soon within the city of Battle Lake.

Hwy 78 remains closed to through-traffic from Battle Lake to Ottertail. In rural areas where crews are paving, flaggers and pilot cars will guide one-way, alternating traffic through the work zone. Additional information about pilot car safety can be found online at www.mndot.gov/d4/projects/hwy78.

Weekly schedule

Work completed the week of Oct. 21:

  • Additional paving completed between Battle Lake and Ottertail
  • Additional concrete curb and gutter poured in Battle Lake

Tentative schedule for the week of Oct. 28 outside of Battle Lake:

  • Paving between Battle Lake and Ottertail

Tentative schedule for the week of Oct. 28 in Battle Lake:

  • Saturday, Oct. 26 – one lift of bituminous through Battle Lake
  • All week - Paving and concrete (sidewalks and curb and gutter) work

Major traffic impacts the week of Oct. 28:

  • Pilot car operations for paving
  • Detour from Ottertail to Battle Lake
  • Battle Lake downtown road closure

Oct. 18

Hwy 78 between Battle Lake and Perham

Paving of Hwy 78 is complete between Perham and Ottertail. Permanent striping and additional shoulder work still needs to be completed in this area.

Crews will continue to pave between Ottertail and Battle Lake. They will work on different segments of the road each day, and flaggers and pilot cars will help local traffic move safely through the work zone.

Flaggers will allow one-way, alternating traffic through the work zone. Drivers must obey the flagger, be prepared to stop and follow the pilot car. Drivers entering Hwy 78 from driveways or intersecting roads within the area being resurfaced must wait for the pilot car to pass in the direction they want to travel, then follow it through the work zone.

Hwy 78 remains closed to through-traffic from Battle Lake to Ottertail. Vehicles are directed onto Hwy 210 and Hwy 108.

Thank you for your patience and cooperation within the Highway 78 work zones.

Weekly detailed schedule

Work completed the week of Oct. 14:

  • Milling complete
  • Additional sidewalks poured
  • Additional paving

Tentative schedule for the week of Oct. 21 outside of Battle Lake:

  • Paving between Co Rd 72 and Ottertail (2 paving operations)

Tentative schedule for the week of Oct. 21 in Battle Lake:

  • Tuesday – railing will be installed by West Battle Lake
  • Paving the first lift through the downtown reconstruction area
  • All week - Concrete sidewalks and curb and gutter construction
  • All week - Graveling roadway

Major traffic impacts the week of Oct. 21:

  • Pilot car operations for paving
  • Detour from Ottertail to Battle Lake
  • Battle Lake downtown road closure

Oct. 11

Hwy 78 between Battle Lake and Perham

Thank you for your patience and cooperation within the Hwy 78 work zones.

Resurfacing of Hwy 78 is nearly complete between Perham and Ottertail.

Crews will continue to work between Ottertail and Battle Lake. They will work on different segments of the road each day, and flaggers and pilot cars will be used to help drivers move safely through the work zone.

Flaggers will allow one-way, alternating traffic through the work zone. Drivers must obey the flagger, be prepared to stop and follow the pilot car. Drivers entering Hwy 78 from driveways or intersecting roads within the area being resurfaced must wait for the pilot car to pass in the direction they want to travel, then follow it through the work zone.

Hwy 78 remains closed to through-traffic from Battle Lake to Ottertail. Vehicles are directed onto Hwy 210 and Hwy 108.

Weekly detailed schedule

Work completed the week of Oct. 7:

  • Additional curb and gutter poured in Battle Lake
  • Milling between Battle Lake and Ottertail
  • Paving between Ottertail and Perham

Tentative schedule for the week of Oct. 14 outside of Battle Lake:

  • Milling from Hwy 210 to the downtown Battle Lake reconstruction area
  • Paving between Co Rd 72 and Ottertail (2 paving operations)

Tentative schedule for the week of Oct. 14 in Battle Lake:

  • All week - Concrete sidewalks and curb and gutter construction
  • All week - Graveling roadway
  • Milling from Hwy 210 north to the reconstruction area

Major traffic impacts the week of Oct. 14:

  • Pilot car operations for milling and paving
  • Detour from Ottertail to Battle Lake
  • Battle Lake downtown road closure

Oct. 4

Hwy 78 between Battle Lake and Perham

Resurfacing of Hwy 78 between Perham and Battle Lake continues. Crews are working south of Perham and north of Battle Lake.

Crews will work on different segments of the road each day, and flaggers and pilot cars will be used to help drivers move safely through the work zone.

Flaggers will allow one-way, alternating traffic through the work zone. Drivers must obey the flagger, be prepared to stop and follow the pilot car. Drivers entering Hwy 78 from driveways or intersecting roads within the area being resurfaced must wait for the pilot car to pass in the direction they want to travel, then follow it through the work zone.

Hwy 78 remains closed to through-traffic from Battle Lake to Ottertail. Vehicles are directed onto Hwy 210 and Hwy 108.

Weekly detailed schedule

Work completed the week of Sept. 30:

  • Curb and gutter poured in Battle Lake
  • Milling complete from Ottertail to Perham
  • Paving began near Perham

Tentative schedule for the week of Oct. 7 outside of Battle Lake:

  • All Week – Milling from County Road 72 north to Ottertail
  • All Week – Paving continues from north to south

Tentative schedule for the week of Oct. 7 in Battle Lake:

  • All week - Concrete sidewalks and curb and gutter construction
  • All week - Graveling roadway
  • End of the week – Milling from Hwy 210 north to the reconstruction area

Major traffic impacts the week of Oct. 7:

  • Pilot car operations for milling and paving
  • Detour from Ottertail to Battle Lake
  • Battle Lake downtown road closure

Sept. 27

Hwy 78 between Battle Lake and Perham

Resurfacing of Hwy 78 between Perham and Battle Lake began this week. Crews will continue working south from the Perham area.

Drivers will experience lane closures and possible delays while the work is underway.

Crews will work on different segments of the road each day, and flaggers and pilot cars will be used to help drivers move safely through the work zone.

Flaggers will allow one-way, alternating traffic through the work zone. Drivers must obey the flagger, be prepared to stop and follow the pilot car. Drivers entering Hwy 78 from driveways or intersecting roads within the area being resurfaced must wait for the pilot car to pass, then follow it through the work zone.

Additional information about pilot car safety can be found online at www.mndot.gov/d4/projects/hwy78.

Hwy 78 remains closed to through-traffic from Battle Lake to Ottertail. Local residents and motorists accessing businesses located within the closure area may use Hwy 78. The signed detour between Battle Lake and Ottertail uses Hwy 210 and Hwy 108. A detour map is also available on the project website.

Lake Avenue between Holdt Street and Summit Street is closed in Battle Lake, and traffic is detoured to adjacent streets.

Weekly detailed schedule

Work completed the week of Sept. 23:

  • Sidewalks poured next to most businesses in Battle Lake
  • Milling and paving work began near Perham

Tentative schedule for the week of Sept. 30 outside of Battle Lake:

  • All Week – Milling and paving work from north to south

Tentative schedule for the week of Sept. 30 in Battle Lake:

  • All week - Sub-grade excavation and graveling sidewalks
  • All week - Concrete sidewalks and curb and gutter construction
  • All week - Graveling roadway

Major traffic impacts the week of Sept. 30:

  • Pilot car operations for milling and paving
  • Detour from Ottertail to Battle Lake
  • Battle Lake downtown road closure

Sept. 20

Hwy 78 between Battle Lake and Perham

Resurfacing of Hwy 78 between Perham and Battle Lake is expected to begin on Monday, Sept. 23. Crews will start working near Perham and proceed south toward Battle Lake.

Drivers will experience lane closures and possible delays for approximately one month while the work is underway.

Crews will work on different segments of the road each day, and flaggers and pilot cars will be used to help drivers move safely through the work zone.

Flaggers will allow one-way, alternating traffic through the work zone. Drivers must obey the flagger, be prepared to stop and follow the pilot car. Drivers entering Hwy 78 from driveways or intersecting roads within the area being resurfaced must wait for the pilot car to pass, then follow it through the work zone.

Hwy 78 remains closed to through-traffic from Battle Lake to Ottertail. Local residents and motorists accessing businesses located within the closure area may use Hwy 78.

The signed detour between Battle Lake and Ottertail uses Hwy 210 and Hwy 108. A detour map is also available on the project website.

Lake Avenue between Holdt Street and Summit Street is closed in Battle Lake, and traffic is detoured to adjacent streets.

Weekly detailed schedule

Work completed the week of Sept. 16:

  • All underground work complete in Battle Lake

Tentative schedule for the week of Sept. 23 outside of Battle Lake:

  • Monday, Sept. 23 and Tuesday, Sept. 24: Turn lane near County Road 128
  • Monday, Sept. 23 and on-going: Milling (removal of a layer of existing pavement) begins in Perham
  • Tuesday, Sept. 24 and on-going: Paving begins in Perham

Tentative schedule for the week of Sept. 23 in Battle Lake:

  • All week – Sub-grade excavation and graveling sidewalks
  • All week - Concrete sidewalks and curb and gutter being constructed
  • All week - Graveling roadway

Major traffic impacts the week of Sept. 23:

  • Pilot car operation begins for milling and paving
  • Detour from Ottertail to Battle Lake
  • Battle Lake downtown road closure

Sept. 13

Work completed the week of Sept. 9:

  • Water main complete in Battle Lake
  • Concrete removal complete in Battle Lake
  • Centerline culvert work complete

Tentative schedule for the week of Sept. 16:

  • Turn lanes between Battle Lake and Perham:
    • Monday, Sept. 16 to Wednesday, Sept. 18: Complete turn lane work
  • Downtown Battle Lake:
    • All week – Begin work on sidewalks
    • All week – Begin curb and gutter work
    • All week – Work on water tie-ins

Major traffic impacts the week of Sept. 16:

  • Detour from Ottertail to Battle Lake
  • Battle Lake downtown road closure

 

Sept. 6

Hwy 78 will remain closed to through-traffic from Battle Lake to Ottertail into October. However, local residents and motorists accessing businesses located within the closure area may use Hwy 78.

Resurfacing of Hwy 78 from Perham to Battle Lake will begin in mid-September.

Work completed the week of Sept. 3:

  • Center lane culvert closures complete Friday
  • Sewer and water main complete in Battle Lake
  • Curb & gutter and sidewalk removal in Battle Lake will be complete Friday

Tentative schedule for the week of Sept. 9:
Culverts & Turn lanes

  • Friday: working on culvert south of Elmer’s Texas BBQ
  • Saturday: No Work
  • Monday: Working on culvert end slopes
  • Tuesday: Working on culvert end slopes
  • Wednesday:  Turn Lane County Road 5
  • Thursday: Turn Lane County Road 5
  • Friday: Turn Lane County Road 128
  • Saturday:  Turn lane County Road 128

Battle Lake

  • Working on tie-ins to businesses
  • Storm pipe installation
  • Sub grade excavation and graveling sidewalks
  • End of week - sidewalk and curb and gutter being placed

Major traffic impacts the week of Sept. 9:

  • Detour from Ottertail to Battle Lake
  • Battle Lake downtown road closure

 

Aug. 30

Hwy 78 between Battle Lake and Perham

Hwy 78 remains closed to through-traffic from Battle Lake to Ottertail. Local residents and motorists accessing businesses located within the closure area may use Hwy 78, but please note that the road will not be passable at culvert replacement sites. Highway 78 between Ottertail and Perham remains open, however, lane closures and delays are possible where crews construct turn lanes.

The signed detour between Battle Lake and Ottertail uses Highway 210 and Highway 108. The detour is scheduled to last through early October.

We estimate the resurfacing of Hwy 78 from Perham to Battle Lake will begin in mid-Sept.

Battle Lake reconstruction

Lake Avenue between Holdt Street and Summit Street is closed in Battle Lake, and traffic is detoured to adjacent streets.

Alternate accesses to business are being established, as needed.

Weekly detailed schedule

Work completed the week of Aug. 26:

  • North detour complete
  • All Culverts in north detour paved
  • Bituminous removal in Battle Lake complete

Tentative schedule for the week of Sept. 3:

  • Culverts & Turn lanes:
    • Friday, Aug. 30: Culvert south of Elmer’s Texas BBQ
    • Saturday, Aug. 31: No work
    • Monday, Sept. 2: No work
    • Tuesday, Sept. 3: Culvert south of Elmer’s Texas BBQ
    • Wednesday, Sept. 4: Culvert West of Madsen’s Resort
    • Thursday, Sept. 5: Culvert West of Madsen’s Resort
    •  Friday, Sept. 6: Culvert West of Madsen’s Resort
    •  Saturday, Sept. 7: Turn lane at Co Rd 5
  • Downtown Battle Lake:
    • All week - Working on water main
    • Tuesday, Sept. 3 and Wednesday, Sept. 4: Sidewalk and curb/gutter removal
    • Tuesday, Sept. 3: Light pole removal

Major traffic impacts the week of Sept. 3:

  • Detour from Ottertail to Battle Lake
  • Battle Lake downtown road closure

Aug. 23

Hwy 78 between Battle Lake and Perham

Hwy 78 detours will change on Monday, Aug. 26. Hwy 78 will reopen between Perham and Ottertail, and the highway will close from Battle Lake to Ottertail. Local residents and motorists accessing businesses located within the closure area may use Hwy 78, but please note that the road will not be passable at culvert replacement sites. Cross roads will remain open.

Traffic will be diverted to Hwy 210 and Hwy 108. This detour is scheduled to last through early October. A map is available below.

Even though the road will reopen, motorists will still encounter occasional lane closures on Hwy 78 between Perham and Ottertail.

We estimate the resurfacing of Hwy 78 from Perham to Battle Lake will begin in mid-September. The schedule shows the entire project wrapping up in mid-October.

Battle Lake reconstruction

Hwy 78/Lake Avenue reconstruction in Battle Lake also will begin Aug. 26. A parking ban will take effect Sunday evening, Aug. 25, so crews can begin removing the existing pavement Monday morning.

Once work begins, Lake Avenue between Holdt Street and Summit Street will close, and traffic will detour to adjacent streets.

The current sidewalks and curbing will remain in place through Labor Day. Alternate business accesses will be established, as needed.

The following businesses want to remind customers to use the side or back entrances during construction:

Creative Cuts
Carlson Highland & Co
Art of the Lakes
Battle Lake Hardware
The Main attraction
Everts Lumber
Prairie Needles
Old Brick Inn
First National Bank (Click here for the access route during construction – opens as a 4.6 MB pdf)
Beads & More

Weekly detailed schedule

Work completed the week of Aug. 19:

  • Culverts north of Co Rd 54
  • Guardrail work completed

Tentative schedule for the week of Aug. 26:

  • Culvert replacements & Turn lane construction:
    • Friday, Aug. 23: Culverts near the railroad tracks
    • Saturday, Aug. 24: Culvert north of the railroad tracks
    • Monday, Aug. 26: Culvert in Ottertail (Motorists will encounter flaggers during this work)
    • Tuesday, Aug. 27: Turn lane at Co Rd 54 (Also milling on culverts between Ottertail and Battle Lake)
    • Wednesday, Aug. 28: Bypass lane at Co Rd 54
    • Thursday, Aug. 29: Bypass lane at Co Rd 54
    •  Friday, Aug. 30: Turn lane south of Co Rd 54
    •  Saturday, Aug. 31: Turn lane south of Co Rd 54
  • Battle Lake:

Monday, Aug. 26 & Tuesday, Aug. 27: Milling existing pavement
Tuesday, Aug. 27: Sewer and water main construction will begin
Major traffic impacts the week of Aug. 26:

  • Detour from Ottertail to Battle Lake will start Monday afternoon
  • Battle Lake downtown road closure will start Monday afternoon
  • Road closures at culvert locations

Aug. 16

Phase one of the Hwy 78 project will continue next week. Hwy 78 remains closed to through-traffic as crews will replace several culverts. Local residents and motorists accessing businesses located within the closure area may use Hwy 78, but please note that the road will not be passable at culvert replacement sites. Cross roads will remain open.

The signed detour runs from Perham east onto Hwy 10 to New York Mills, south on Co Rd 67 and west on Co Rd 52/Hwy 108 to Ottertail. A detour map is available on the project website, www.mndot.gov/d4/projects/hwy78.

Work completed the week of Aug. 12:

  • Culvert partially completed 1 ½ mile south of Hwy 108 near Perham
  • Guardrail removed at Hwy 10 bridge and Rush Lake (Otter Tail River) bridge
  • Concrete end post complete on Rush Lake (Otter Tail River) bridge
  • Milling and saw cutting at culvert locations complete

Tentative schedule for the week of Aug. 19:

  • Culvert Replacements:
    • Friday, Aug. 16:  South of Rush Lake (Otter Tail River) bridge
    • Saturday, Aug. 17: Complete culvert work 1 ½ miles south of Hwy 108 near Perham
    • Monday, Aug. 19: South of Rush Lake (Otter Tail River) bridge north of Co Rd 54
    • Tuesday, Aug. 20: South of Rush Lake (Otter Tail River) bridge north of Co Rd 54
    • Wednesday, Aug. 21: One-half mile south of Co Rd 54
    • Thursday, Aug. 22: Just north of railroad tracks (north of Ottertail)
    •  Friday, Aug. 23: Just south of the railroad tracks (north of Ottertail)
    •  Saturday, Aug. 24: About ½ mile north of Hwy 108 in Ottertail
  • Bridge work:

Concrete end post complete Tuesday
Guardrail installed Wednesday and Thursday

Major traffic impacts the week of Aug. 19:

  • Detour from Perham to Ottertail
  • Road closures at culvert locations

Once culverts are replaced north of Ottertail, Hwy 78 from Ottertail to Battle Lake will close for similar culvert replacement work. That is also the point when work will begin on the reconstruction of Lake Avenue in downtown Battle Lake. We anticipate this work will begin in late August.

Resurfacing of Hwy 78 from Perham to Battle Lake will begin after culverts work is complete. The schedule shows the entire project wrapping up in mid-October.

Aug. 9

Work will begin Monday, Aug. 12 between Perham and Ottertail. During this phase of the project, Hwy 78 will close to through-traffic and crews will replace several culverts. Local residents and motorists accessing businesses located within the closure area may use Hwy 78, but please note that the road will not be passable at culvert replacement sites. Cross roads will remain open.

The signed detour runs from Perham east onto Hwy 10 to New York Mills, south on County Road 67 and west on County Road 52/Hwy 108 to Ottertail. It will be up for approximately three weeks. A detour map is available below.

Specific work planned for the week of Aug. 12:

  • Milling at eight culvert locations between Perham and Ottertail
  • Culvert replacements from north to south within the detour zone
  • Construct two turn lanes approximately two miles north of Ottertail
  • Guard rail work at the Hwy 10 bridge in Perham and the Otter Tail River bridge
  • Installation of erosion control devices between Perham and Ottertail

Major traffic impacts the week of Aug. 12:

  • Detour from Perham to Ottertail
  • Road closures at culvert locations

Once culverts are replaced north of Ottertail, Hwy 78 from Ottertail to Battle Lake will close for similar culvert replacement work. That is also the point when work will begin on the reconstruction of Lake Avenue in downtown Battle Lake. We anticipate this work will begin in late August.

Resurfacing of Hwy 78 from Perham to Battle Lake will begin after culverts work is complete. The schedule shows the entire project wrapping up in mid-October.