Minnesota Department of Transportation Go to 511
MnDOT A to Z | General Contacts | Simple Search | Advanced Search

Highway 95 Princeton
Roundabout & Bridge Construction at Mille Lacs County Road 29

Generic Traffic Stock Photo
Project Main
Project Photos
About Roundabouts
District 3 Construction
Statewide Roadwork
Contacts

Project Photos - Project is Complete
Click on image to view high resolution photo.

 

 

River Cutting Ceremony
Nov. 19, 2010 - Ribbon Cutting Ceremony held at park. Bridges and roundabout opens to traffic.

River Cutting Ceremony
Nov. 19, 2010 - Ribbon Cutting Ceremony held at park, followed by a parade, and then the bridges and roundabout was opened to traffic.

Hwy 95 Deck with railing installedNov. 17, 2010 - Crews finish installing the railing on the Hwy 95 bridge.

Installing arches
Nov. 2, 2010 - Crews install the decorative arches on the sides of the bridges.

Installing arches
Nov. 2, 2010 - Crews install the decorative arches on the sides of the bridges.

roundabout constructionOct. 18, 2010. Roundabout construction. Curbs installed.

Roundabout constructionOct. 13, 2010 - Roundabout construction.

Hwy 95Oct. 5, 2010 - Dunn River bridge construction; bridge deck has been poured.

 

Roundabout construction begins Sept. 20!Aug. 20, 2010 - Crews begin to construct the roundabout at Hwy 95 and Mille Lacs County Rd 29.

Roundabout graphic

Roundabout graphic

Dunn River bridge- High waters at construction site
Aug. 19, 2010 - Heavy Area Rains Delay Work - Due the unusually heavy rains this time of year and the rise in the river elevations to almost 9 feet, the bridge contractor has been unable to complete critical work tasks within the proposed schedule.

We are currently evaluating the impact of these rain delays and the schedule will be revised. The contractor will continue to work to make up for these weather-related delays. However, this project was on an aggressive schedule and these extreme weather condition may have an effect on the completion date.

At this point, we anticipate that crews will be returning to work on Monday, August 23.

Dunn River bridge site
Aug. 3, 2010 - Dunn River bridge site - Crews install form rebar for the north abutment. Next week concrete will be poured into the forms. Photo by Bryon Amo

Dunn River site
July 21, 2010 - Dunn River bridge site - crews have completed constructing pier #2, and continue to pour concrete into pier #1. Work has begun on the future north bridge abutment. Photo by Bryon Amo

River Cutting Ceremony
Nov. 19, 2010 - Ribbon Cutting Ceremony held at park near Dunn River Bridge.

River Cutting Ceremony
Nov. 19, 2010 - Ribbon Cutting Ceremony held at park, followed by a parade, and then the bridges and roundabout was opened to traffic.

River Cutting Ceremony
Nov. 19, 2010 - Ribbon Cutting Ceremony held at park. Bridges and roundabout opens to traffic.


Roundabout Opens to Traffic Night Image
Nov. 5, 2010 - The north and west roadway and sidewalks opened to traffic late Friday afternoon, Nov. 5. Traffic can move through the roundabout intersection to and from the north and west.

Roundabout Construction
Oct. 27, 2010 - The concrete work is nearly complete, including the sidewalks around the roundabout. State of the art LED street lighting has been installed along the roadway and will be tested.

roundabout constructionOct. 18, 2010 - Crews grade and compact soils in the roundabout construction area.

Roundabout constructionOct. 13, 2010 - Roundabout construction from the Mille Lacs County Rd 29 bridge abutment.

Hwy 95Oct. 13, 2010 - Highway 95 bridge construction; bridge deck has been poured.

Mille Lacs County Rd 29/Dunn River bridge constructionAug. 20, 2010 - Crews install forms for the the future Mille Lacs County Rd 29/Dunn River Bridge deck surface.

flooding waters
Aug. 19, 2010 - Heavy area rains flood construction sites.

Hwy 95 bridge site
July 21, 2010 - Hwy 95 bridge site - The footing foundation for pier #2 has been constructed. Crews have installed a coffer dam to construct pier #1. Workers will continue to construct piers next week. Photo by Bryon Amo

Groundbreaking Ceremony at Riverside Park in Princeton. Approximately 50 guests attended.
July 2, 2010 - Hwy 95 bridge site - Crews prepare and build pier #2's frames for the future bridge. Drilling of support piling for bridge pier #2 begins next week. Excavation preparation work continues for bridge pier #1.

Week of June 7, 2010 - Crews dismantle the Dunn River Bridge.
June 17, 2010 - Crews dismantle the Hwy 95 bridge.

Groundbreaking Ceremony at Riverside Park in Princeton. Approximately 50 guests attended.
July 2, 2010 - Dunn River bridge site - crews pour concrete into the bridge pier #2's frame for the future bridge. Excavation preparation work continues for pier #1 and on the north side bridge abutment.

Hwy 95 Bridge with installed railingNov. 17, 2010 - Crews finish installing the railing on the Hwy 95 bridge.

River Cutting Ceremony
Nov. 19, 2010 - Ribbon Cutting Ceremony - parade. Bridges and roundabout opens to traffic. Princeton Band plays in background.

River Cutting Ceremony
Nov. 19, 2010 - Ribbon Cutting Ceremony held at park, followed by a parade, and then the bridges and roundabout was opened to traffic.

Installing decorative archesNov. 2, 2010 - Crews install the decorative arches on the sides of the bridges.

Install decorative arches
Nov. 2, 2010 - Crews install the decorative arches for each span of the bridge. Far right shows one installed, middle not installed yet.

Bridge
Oct. 27, 2010 - Due to unusually high water this time of year, limited work was completed on the bridges this past week. The high water has delayed  installation of the precast decorative concrete arches that will be placed on each side of the bridges on each span.

Hwy 95 bridgeOct. 13, 2010 - Highway 95 bridge construction; bridge deck has been poured.

Hwy 95 bridge construction siteAug. 20, 2010 - Progress continues on the Hwy 95 bridge.

Hwy 95 Bridge Site: High waters at construction site
Aug. 19, 2010 - Heavy area rains flood construction sites.

Week of June 7, 2010 - Crews dismantle the Dunn River Bridge.
June 17, 2010 - Crews dismantle the Hwy 95 bridge.

Week of June 7, 2010 - Crews dismantle the Dunn River Bridge.
Week of June 7, 2010 - Crews dismantle the Dunn River Bridge using two cranes.
Groundbreaking Ceremony at Riverside Park in Princeton. Approximately 50 guests attended.
June 17, 2010 - Dunn River bridge site; main old bridge spans over river removed.
Week of June 7, 2010 - Crews dismantle the Dunn River Bridge.
Week of June 7, 2010 - Crews dismantle the Dunn River Bridge.
Groundbreaking Ceremony at Riverside Park in Princeton. Approximately 50 guests attended.
June 3, 2010 - Groundbreaking Ceremony at Riverside Park in Princeton. Approximately 50 guests attended.

 


Pay Attention or Pay the Price

Go to Top

blank