Nov. 19, 2010 - Ribbon Cutting Ceremony held at park. Bridges and roundabout opens to traffic.

Nov. 19, 2010 - Ribbon Cutting Ceremony held at park, followed by a parade, and then the bridges and roundabout was opened to traffic.
Nov. 17, 2010 - Crews finish installing the railing on the Hwy 95 bridge.

Nov. 2, 2010 - Crews install the decorative arches on the sides of the bridges.

Nov. 2, 2010 - Crews install the decorative arches on the sides of the bridges.
Oct. 18, 2010. Roundabout construction. Curbs installed.
Oct. 13, 2010 - Roundabout construction.
Oct. 5, 2010 - Dunn River bridge construction; bridge deck has been poured.
Aug. 20, 2010 - Crews begin to construct the roundabout at Hwy 95 and Mille Lacs County Rd 29.

Roundabout graphic

Aug. 19, 2010 - Heavy Area Rains Delay Work - Due the unusually heavy rains this time of year and the rise in the river elevations to almost 9 feet, the bridge contractor has been unable to complete critical work tasks within the proposed schedule.
We are currently evaluating the impact of these rain delays and the schedule will be revised. The contractor will continue to work to make up for these weather-related delays. However, this project was on an aggressive schedule and these extreme weather condition may have an effect on the completion date.
At this point, we anticipate that crews will be returning to work on Monday, August 23.

Aug. 3, 2010 - Dunn River bridge site - Crews install form rebar for the north abutment. Next week concrete will be poured into the forms. Photo by Bryon Amo
|

July 21, 2010 - Dunn River bridge site - crews have completed constructing pier #2, and continue to pour concrete into pier #1. Work has begun on the future north bridge abutment. Photo by Bryon Amo |
|

Nov. 19, 2010 - Ribbon Cutting Ceremony held at park near Dunn River Bridge.

Nov. 19, 2010 - Ribbon Cutting Ceremony held at park, followed by a parade, and then the bridges and roundabout was opened to traffic.

Nov. 19, 2010 - Ribbon Cutting Ceremony held at park. Bridges and roundabout opens to traffic.

Nov. 5, 2010 - The north and west roadway and sidewalks opened to traffic late Friday afternoon, Nov. 5. Traffic can move through the roundabout intersection to and from the north and west.

Oct. 27, 2010 - The concrete work is nearly complete, including the sidewalks around the roundabout. State of the art LED street lighting has been installed along the roadway and will be tested.
Oct. 18, 2010 - Crews grade and compact soils in the roundabout construction area.
Oct. 13, 2010 - Roundabout construction from the Mille Lacs County Rd 29 bridge abutment.
Oct. 13, 2010 - Highway 95 bridge construction; bridge deck has been poured.
Aug. 20, 2010 - Crews install forms for the the future Mille Lacs County Rd 29/Dunn River Bridge deck surface.

Aug. 19, 2010 - Heavy area rains flood construction sites.

July 21, 2010 - Hwy 95 bridge site - The footing foundation for pier #2 has been constructed. Crews have installed a coffer dam to construct pier #1. Workers will continue to construct piers next week. Photo by Bryon Amo
|

July 2, 2010 - Hwy 95 bridge site - Crews prepare and build pier #2's frames for the future bridge. Drilling of support piling for bridge pier #2 begins next week. Excavation preparation work continues for bridge pier #1.
|
|

June 17, 2010 - Crews dismantle the Hwy 95 bridge.
|

July 2, 2010 - Dunn River bridge site - crews pour concrete into the bridge pier #2's frame for the future bridge. Excavation preparation work continues for pier #1 and on the north side bridge abutment.
|
Nov. 17, 2010 - Crews finish installing the railing on the Hwy 95 bridge.

Nov. 19, 2010 - Ribbon Cutting Ceremony - parade. Bridges and roundabout opens to traffic. Princeton Band plays in background.

Nov. 19, 2010 - Ribbon Cutting Ceremony held at park, followed by a parade, and then the bridges and roundabout was opened to traffic.
Nov. 2, 2010 - Crews install the decorative arches on the sides of the bridges.

Nov. 2, 2010 - Crews install the decorative arches for each span of the bridge. Far right shows one installed, middle not installed yet.

Oct. 27, 2010 - Due to unusually high water this time of year, limited work was completed on the bridges this past week. The high water has delayed installation of the precast decorative concrete arches that will be placed on each side of the bridges on each span.
Oct. 13, 2010 - Highway 95 bridge construction; bridge deck has been poured.
Aug. 20, 2010 - Progress continues on the Hwy 95 bridge.

Aug. 19, 2010 - Heavy area rains flood construction sites.
|
|

June 17, 2010 - Crews dismantle the Hwy 95 bridge.
|

Week of June 7, 2010 - Crews dismantle the Dunn River Bridge using two cranes. |

June 17, 2010 - Dunn River bridge site; main old bridge spans over river removed.
|

Week of June 7, 2010 - Crews dismantle the Dunn River Bridge. |

June 3, 2010 - Groundbreaking Ceremony at Riverside Park in Princeton. Approximately 50 guests attended. |
|