Highway 371
Four lane expansion from Nisswa to Pine River
Project Home | Background | Documents | Maps | Photos | Schedule | Study Process | ADA |Future Projects Statewide | Contacts

Schedule

 

Year
Activity
December 2002
Public Scoping Meeting
February 2003
Final Scoping Decision Document
November 2003
Amended Scoping Decision Document
December 2003 Start of Draft Environmental Impact Statement
January 2004 Public Hearing on Draft Environmental Impact Statement
March 2004 Selection of Preferred Alternative by MnDOT
January 2005 Distribution of Final Environmental Impact Statement
March 2005 Federal Highway Administration Record of Decision
March 2005 MnDOT Adequacy Determination
June 2006 City of Pequot Lakes requests realignment alternative
September 2007 Pequot Lakes joint committee publishes Highway 371 Alternate Route Study Group Report
December 2008 Pequot Lakes City Council Passes Resolution Identifying the Bypass as the Preferred Alternative
February 2010 MnDOT Draft Supplemental Final Environmental Impact Statement (SFEIS) for Pequot Lakes bypass
Mar. 8 - April 16, 2010 Draft SFEIS available for public review and comments
Mar. 29 - 30, 2010 Draft SFEIS Public Hearings in Pequot Lakes and Pine River
May - July 2010 Complete Final SFEIS
October 2010 Federal Highway Administration Record of Decision
November - December 2010 Municipal Consent (Nisswa, Pequot Lakes and Jenkins)
2012 - 2013 Realignment construction of Main Street/Crow Wing County Road 18 in Nisswa
2012 - 2016 Final Design and Property Acquisition
2018-2019 Construction begins from Nisswa to Jenkins
Beyond 2029 Construction begins from Jenkins to Pine River

 

Future dates subject to change.

 