
Nov. 10, 2008 - Seventy-five piles were set into place
for drilling that will make-up the west pier foundation.
The piles will be driven approximately 65 feet down
from the water line. A coffer dam surrounds the piles.
Photo by Kevin Kiess
|

Oct. 10, 2008 - Crews prep the west pier for detonation
by drilling down into the concrete for explosive placement.
Rubber matting is affixed on-top the structure to hold
in debris. Photo by Peter Leete
|

Sept. 29, 2008 - The 121-foot mid-span taken down and
put onto a two barges. Photo by Kevin Kiess
|

Sept. 22, 2008 - A crane on a barge. Construction workers
illustrates the magnitude of the size of the 210-ton crane.
Photo by Kevin Kiess
|

Sept. 15, 2008 - Crushing jaws are used to demolish removed
concrete into smaller pieces so it can be hauled away.
Photo by Kevin Kiess
|

Sept. 12, 2008 - Morning fog frames the steel Desoto bridge
structure. Crews have completed removing the concrete
deck. Photo by Kevin Kiess
|

Sept. 3, 2008 - A backhoe with a "crab claw"
attachment is used to remove sections of the concrete
deck. Each section weighs about 10-11,000 lbs. Photo
by Kevin Kiess
|

Oct. 1, 2008 - Kevin Kiess, MnDOT chief field inspector
for the bridge project. Photo by Jenny Seelen |

Aug. 27, 2008 - A contractor's employee saws the sidewalk
and bridge railing into sections for removal. Photo
by Jenny Seelen |
|

Nov. 4, 2008 - Crews install new sewer pipes that will
be under Riverside Drive. Photo by Kevin Kiess
|

Oct. 29, 2008 - Crews demolish and remove the concrete
eastside bridge approach at Riverside Drive. Photo
by Kevin Kiess
|

Oct. 10, 2008 - Before detonation, everyone is evacuated
to safe zones away from the blast site. After the all
clear, crews implode the west pier. Photo by Peter
Leete
|

Sept. 29, 2008 - Worker's use cutting rod tourches to
cut steel into sections. Photo by Kevin Kiess
|

Sept. 29, 2008 - A 210-ton crane is driven onto a barge
to start the step of taking down the steel of the structure.
Photo by Kevin Kiess
|

Sept. 15, 2008 - Barge moved to bridge site using tug
boat. Photo by Kevin Kiess
|

Sept. 12, 2008 - Barges being docked and prepared for
the bridge site. Photo by Kevin Kiess
|

Sept. 3, 2008 - Crews begin to remove the old bridge deck/concrete
roadway in sections. Photo by Kevin Kiess
|

Aug. 27, 2008 - Crews remove the concrete stairway and
Riverside Avenue pavement underneath the eastside of the
bridge. Photo by Jenny Seelen |
|

Oct. 10, 2008 - The west pier is imploded for removal.
Photo by Peter Leete |

Oct. 1, 2008 - Steel sections of the old DeSoto bridge
are lifted off the barge onto the riverside. The steel
is then hauled away to be recycled. Photo by Jenny
Seelen
|

Oct. 1, 2008 - Worker's use cutting rod tourches to cut
steel into sections. Photo by Kevin Kiess
|

Sept. 15, 2008 - Crushing jaws are used to demolish removed
concrete into smaller pieces so it can be hauled away.
Photo by Kevin Kiess
|

Sept. 3, 2008 - Crews begin to remove the old bridge deck/concrete
roadway in sections. Photo by Kevin Kiess
|

Sept. 3, 2008 - Crews cut steel. Photo by Kevin Kiess
|

Sept. 3, 2008 - Crews remove sections of the concrete
sidewalk off the bridge. Photo by Kevin Kiess |

Sept. 3, 2008 - Bridge deck with sidewalk removed. Photo
by Kevin Kiess |

Aug. 27, 2008 - Micky Klasen, MnDOT District 3 bridge
supervisor (at right), and Bruce Reihl, Lunda Construction
Project Superintendent, observe the sidewalk and road
removal. Photo by Jenny Seelen |
|