|

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Oct. 26 - Hwy 23 Granite City Crossing Bridge fall sunset. Photo by Dan Gilder

Oct. 27 - Crews install a sewer pipe lining. Photo by Jesse Hudec

Oct. 27 - Crews install a sewer pipe lining. Photo by Jesse Hudec

Oct. 21 - Hwy 23 Granite City Crossing Bridge with granite veneer, railing, and light posts installed. Photo by Dan Gilder

Sept. 2 - Pedestrian overlook from below the bridge. Photo by Jenny Seelen

Sept. 2 - Concrete street curb machinery. Photo by Jenny Seelen

Sept. 2 - Crews install concrete street curbs. Photo by Jenny Seelen

Sept. 2 - Crews install concrete side-street curbs near Wilson Avenue. Photo by Jenny Seelen

July 2009 - Crews install deck reinforcement rebar. Photo
by Jesse Hudec

July 2009 - Installed bridge deck reinforcement rebar at the
westend approach. Photo by Jesse Hudec

July
2009 - Crews install deck reinforcement rebar. Photo by
Jesse Hudec

July 2009 - Crews install deck forms. Photo by Dan Gilder
low.jpg)
June 10, 2009 - The bridge is connected! The mid-span
girder is installed. Photo by Jesse Hudec
low.jpg)
June 6, 2009 - A girder is lifted up by a crane. Photo
by Jesse Hudec

June 6, 2009 - A girder sits on a floating dock station as
a tug boat drives it out so it can be lifted into place. Photo
by Jesse Hudec
low.jpg)
June 6, 2009 - Crews tighten bolts that connect the two girders
together. Photo by Jesse Hudec

May 14, 2009 - Second arrival of girders. Photo by Jenny
Seelen

May 14, 2009 - Second arrival of girders. Photo by Jenny
Seelen

May 14, 2009 - Crane operator. Photo by Jenny Seelen

May 14, 2009 - Second arrival of girders. Photo by Jenny
Seelen

May 14, 2009 - Construction site Photo by Jenny Seelen

May 5, 2009 - First arrival - one of the steel girder sections.
Photo by Kevin Kiess

May 8, 2009 - Two cranes lift the first steel girder section
off the semi-trailer onto the pier. Photo by Kevin Kiess

May 8, 2009 - The steel girders make-up the substructure
that supports the bridge deck. This is one section of a two-piece
girder that will be connected together to form one span. It
weighs approximately 32 tons and is 133 feet long. Photo
by Kevin Kiess

May 8, 2009 - Two cranes lift the first steel girder section
onto the east end pier. Photo by Kevin Kiess

May 2009 - The first steel girders leave the factory plant
in Gary, Indiana. Photo provided by Industrial Steel Construction

April 23, 2009 - Crews work on the west abutment.Photo
by Kevin Kiess
low.jpg)
March 3, 2009 - Top cap of the west pier - tied steel rebar.
Photo by Kevin Kiess

Jan. 29, 2009 - The "Sea-Breeze" traveling through
the icy Mississippi River. Photo by Kevin Kiess

Jan. 29, 2009 - Work continues on the piers. Photo by Kevin
Kiess
|

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Nov. 18 - Hwy 23 city installed banner signs on light fixtures. Photo by Jenny Seelen

Nov. 18 - Hwy 23 city installed banner signs. Photo by Jenny Seelen

Oct. 29 - Hwy 23 Granite City Crossing Bridge. Photo by Jesse Hudec

Oct. 28 - Crews wash the bridge deck. Photo by Dan Gilder

Oct. 21 - The newly installed Hwy 23 Granite City Crossing Bridge number and construction date stamp plate. Photo by Dan Gilder

Sept. 2 - Future pedestrian sidewalk overlook from the bridge deck. Photo by Jenny Seelen

Sept. 2 - Hwy 23 Mississippi River bridge from the eastside looking west. Photo by Jenny Seelen

Sept. 2 - Hwy 23 Mississippi River bridge from the center of the deck looking south. Photo by Jenny Seelen

Sept. 2 - Crane on a floating dock lifting up a plateform below the bridge so crews can remove the wood forms underneath the bridge deck. The forms were used for the concrete deck construction. Photo by Jenny Seelen

Sept. 4 - Crane on a floating dock below is lifting a plateform (red) to below the bridge so crews can remove the wood forms underneath the bridge deck. The wood forms were used for the deck construction. Photo by Jenny Seelen

Sept. 2 - Hwy 23 Mississippi River Bridge deck looking west towards 4th Avenue. Photo by Jenny Seelen

August 2009 - The floating barges on the Mississippi River
used for construction are no longer needed. Crews remove them
out of the water and steam wash them clean. Photo by Dan
Gilder

August 2009 - A worker steam washes the barge clean before
it gets hauled away to storage. Photo by Dan Gilder

August 2009 - The cleaned barge is loaded on a semi-trailer
to be hauled back to storage for the next bridge project.
Photo by Dan Gilder

July 2009 - Crews work on the eastend roadway approaches at
Wilson Avenue. Photo by Dan Gilder
low.jpg)
June 6, 2009 - Workers tighten bolts that connect the two
girders together. Photo by Jesse Hudec
low.jpg)
June 10, 2009 - Crews install the mid-span girder. Photo
by Jesse Hudec
low.jpg)
June 6, 2009 - Crews wait for the girder to be lifted into
place so they can tighten the bolts that hold the two girders
together. Photo by Jesse Hudec

May 14, 2009 - Crews unload the haunch girders that will be
placed on pier #2. Photo by Jenny Seelen

May 14, 2009 - Second arrival of girders. Photo by Jenny
Seelen

May 12, 2009 - Construction site. Photo by Jenny Seelen

May 12, 2009 - Construction site. Photo by Jenny Seelen

May 12, 2009 - Construction site. Photo by Jenny Seelen

May 8, 2009 - Two cranes lift the first steel girder section
off the semitrailer onto the pier. Photo by Kevin Kiess

May 12, 2009 - Construction site. Photo by Jenny Seelen

May 8, 2009 - Two cranes lift the first steel girder section
onto the pier. Photo by Kevin Kiess

May 2009 - The first steel girders leave the factory plant
in Gary, Indiana. Photo provided by Industrial Steel Construction

April 23, 2009 - Crews assemble crossbraces to be installed
between the piers. Photo by Kevin Kiess
low.jpg)
March 3, 2009 - Installed rebar and wood framing ready for
concrete pouring. Photo by Kevin Kiess
|

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Oct. 29 - Hwy 23 Granite City Crossing Bridge ped sidewalk construction at Riverside Drive. Photo by Dan Gilder

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Nov. 18 - Hwy 23 Granite City Crossing Bridge. Photo by Jenny Seelen

Oct. 29 - Bridge opens; Pantowners Auto Club is the first to cross. Photo by Dan Gilder

Oct. 29 - Bridge opens; Pantowners Auto Club is the first to cross. Photo by Dan Gilder

Sept. 2 - Crews pour the concrete center median on the bridge deck. Photo by Jenny Seelen

Sept. 2 - Crews pour the concrete center median on the bridge deck. Photo by Jenny Seelen

Sept. 2 - Crews pour the concrete center median on the bridge deck. Photo by Jenny Seelen

Sept. 2 - Crews pour the concrete center median on the bridge deck. Photo by Jenny Seelen
lo.jpg)
July 2009 - Concrete trucks standby to begin the deck pour.
Photo by Jesse Hudec
lo.jpg)
July
2009 - Crews pour the concrete deck beginning at the center
span and moving outward towards the bridge approaches. Photo
by Jesse Hudec
lo.jpg)
July
2009 - Deck pouring. Above is a pipe that is pumping concrete
from the mixer trucks out to the crews pouring the deck surface.
Photo by Jesse Hudec

July 2009 - Crews back-fill soil at the westend approach
reinforcement walls. Photo by Jesse Hudec

July 2009 - Westend reinforcement wall work. Photo
by Jesse Hudec
|
low.jpg)
June 10, 2009 - The new bridge is connected! The first
mid-span girder is set in place. Photo by Jesse Hudec

June 10, 2009 - The bridge is connected! The mid-span
girder is installed. Photo by Kevin Kiess

June 10, 2009 - A girder is lifted up by a crane.
Photo taken from the Veterans Bridge. Photo by Kevin
Kiess

June 10, 2009 - A girder sits on a floating dock station
as a tug boat drives it out to the center where two
cranes will lift it into place. Photo by Kevin Kiess
.jpg)
June 6, 2009 - A steel worker tightens bolts into
the two girders. Photo by Jesse Hudec

May 20, 2009 - Semitrailer hauls a girder to the
construction site - turning off Hwy 10 to Germain Street
in St. Cloud. Photo by Kevin Kiess

May 21, 2009 - Crews place beams at the eastside abutment
where the bridge goes over Riverside Drive. Photo
by Kevin Kiess

May 14, 2009 - Crews unload the haunch girders that
will be placed on pier #2. Photo by Jenny Seelen

May 14, 2009 - Granite veneer work on east abutment.Photo
by Jenny Seelen

April 23, 2009 - Crews install granite veneer on the
east pier. Photo by Kevin Kiess

April 23, 2009 - Workshop tools used by crews installing
granite detailing. Photo by Kevin Kiess

April 23, 2009 - Pier and east abutment.Photo by
Kevin Kiess

April 23, 2009 - Construction site. Photo by Kevin
Kiess
Feb 2009 - Crews work after dark pouring concrete pier
foundations using a pump hose connected from a mixer
truck parked above on the west embankment.

Jan. 29, 2009 - The "Sea-Breeze" traveling
through the icy Mississippi River. Photo by Kevin
Kiess

Jan. 29, 2009 - Crews continue to construct the piers
throughout the winter season. Green steel rebar begins
to be visible. Photo by Kevin Kiess
|

Jan. 29, 2009 - Crews use a flat boat to travel out through
the ice to the pier construction site. Photo by Kevin Kiess
|