|
low.jpg)
June 10, 2009 - The bridge is connected! The mid-span
girder is installed. Photo by Jesse Hudec
low.jpg)
June 6, 2009 - A girder is lifted up by a crane. Photo
by Jesse Hudec

June 6, 2009 - A girder sits on a floating dock station as
a tug boat drives it out so it can be lifted into place. Photo
by Jesse Hudec
low.jpg)
June 6, 2009 - Crews tighten bolts that connect the two girders
together. Photo by Jesse Hudec

May 14, 2009 - Second arrival of girders. Photo by Jenny
Seelen

May 14, 2009 - Second arrival of girders. Photo by Jenny
Seelen

May 14, 2009 - Crane operator. Photo by Jenny Seelen

May 14, 2009 - Second arrival of girders. Photo by Jenny
Seelen

May 14, 2009 - Construction site Photo by Jenny Seelen

May 5, 2009 - First arrival - one of the steel girder sections.
Photo by Kevin Kiess

May 8, 2009 - Two cranes lift the first steel girder section
off the semi-trailer onto the pier. Photo by Kevin Kiess

May 8, 2009 - The steel girders make-up the substructure
that supports the bridge deck. This is one section of a two-piece
girder that will be connected together to form one span. It
weighs approximately 32 tons and is 133 feet long. Photo
by Kevin Kiess

May 8, 2009 - Two cranes lift the first steel girder section
onto the east end pier. Photo by Kevin Kiess

May 2009 - The first steel girders leave the factory plant
in Gary, Indiana. Photo provided by Industrial Steel Construction

April 23, 2009 - Crews work on the west abutment. Photo
by Kevin Kiess
low.jpg)
March 3, 2009 - Top cap of the west pier - tied steel rebar.
Photo by Kevin Kiess

Jan. 29, 2009 - The "Sea-Breeze" traveling through
the icy Mississippi River. Photo by Kevin Kiess
|
low.jpg)
June 6, 2009 - Workers tighten bolts that connect the two girders
together. Photo by Jesse Hudec
low.jpg)
June 10, 2009 - Crews install the mid-span girder. Photo
by Jesse Hudec
low.jpg)
June 6, 2009 - Crews wait for the girder to be lifted into
place so they can tighten the bolts that hold the two girders
together. Photo by Jesse Hudec

May 14, 2009 - Crews unload the haunch girders that will be
placed on pier #2. Photo by Jenny Seelen

May 14, 2009 - Second arrival of girders. Photo by Jenny
Seelen

May 12, 2009 - Construction site. Photo by Jenny Seelen

May 12, 2009 - Construction site. Photo by Jenny Seelen

May 12, 2009 - Construction site. Photo by Jenny Seelen

May 8, 2009 - Two cranes lift the first steel girder section
off the semi-trailer onto the pier. Photo by Kevin Kiess

May 12, 2009 - Construction site. Photo by Jenny Seelen

May 8, 2009 - Two cranes lift the first steel girder section
onto the pier. Photo by Kevin Kiess

May 2009 - The first steel girders leave the factory plant
in Gary, Indiana. Photo provided by Industrial Steel Construction

April 23, 2009 - Crews assemble crossbraces to be installed
between the piers. Photo by Kevin Kiess
low.jpg)
March 3, 2009 - Installed rebar and wood framing ready for
concrete pouring. Photo by Kevin Kiess

Jan. 29, 2009 - Work continues on the piers. Photo by Kevin
Kiess

Jan. 29, 2009 - Crews use a flat boat to travel out through
the ice to the pier construction site. Photo by Kevin Kiess
|
|
low.jpg)
June 10, 2009 - The new bridge is connected! The first
mid-span girder is set in place. Photo by Jesse Hudec

June 10, 2009 - The bridge is connected! The mid-span
girder is installed. Photo by Kevin Kiess

June 10, 2009 - A girder is lifted up by a crane.
Photo taken from the Veterans Bridge. Photo by Kevin
Kiess

June 10, 2009 - A girder sits on a floating dock station
as a tug boat drives it out to the center where two
cranes will lift it into place. Photo by Kevin Kiess
.jpg)
June 6, 2009 - A steel worker tightens bolts into
the two girders. Photo by Jesse Hudec

May 20, 2009 - Semi-trailer hauls a girder to the
construction site - turning off Hwy 10 to Germain Street
in St. Cloud. Photo by Kevin Kiess

May 21, 2009 - Crews place beams at the eastside abutment
where the bridge goes over Riverside Drive. Photo
by Kevin Kiess

May 14, 2009 - Crews unload the haunch girders that
will be placed on pier #2. Photo by Jenny Seelen

May 14, 2009 - Granite veneer work on east abutment.
Photo by Jenny Seelen

April 23, 2009 - Crews install granite veneer on the
east pier. Photo by Kevin Kiess

April 23, 2009 - Workshop tools used by crews installing
granite detailing. Photo by Kevin Kiess

April 23, 2009 - Pier and east abutment. Photo by
Kevin Kiess

April 23, 2009 - Construction site. Photo by Kevin
Kiess
Feb 2009 - Crews work after dark pouring concrete pier
foundations using a pump hose connected from a mixer
truck parked above on the west embankment.

Jan. 29, 2009 - The "Sea-Breeze" traveling
through the icy Mississippi River. Photo by Kevin
Kiess

Jan. 29, 2009 - Crews continue to construct the piers
throughout the winter season. Green steel rebar begins
to be visible. Photo by Kevin Kiess
|
|