Reconstruct 14 miles of road surface, replace/repair pipes and improve access on Highway 210 from the end of the four-lane in Brainerd to Ironton in 2019.

Project location map -
2019 Roadwork: Hwy 210 Brainerd to Ironton. Project requires a detour. Click map for larger PDF version

Summary of work

  • Reconstruct 14 miles of Hwy 210 road surface (full-depth reclamation), includes shoulders and turn-lanes
  • Reconstruct the Hwy 210 and CR 12 (Deerwood shortcut) intersection
  • Repair or replace underground drainage structures, includes pipes:
    • West of CR 147 (Crow Wing County Landfill)
    • West of CR 59
    • West of CR 12 (Deerwood shortcut)
  • Add left turn lanes at CR 25, CR 147 (Crow Wing County Landfill), CR 59
  • Add bypass lanes at the Mississippi Northwoods entrance and Sploezens Rd
  • Install mumble and rumble strips

Future impacts

2019 Traffic plans

Project tentatively scheduled to begin after the week of 4th of July, 2019. Get updates delivered to you inbox. Sign up for email updates.

Detour

Hwy 210 will close to through traffic and detour between Brainerd and Ironton. Seek alternative routes, or use the signed detour along Hwy 25 Brainerd, Hwy 18 to Hwy 6 Deerwood and Hwy 6/Hwy 210 to Crosby-Ironton.

Local access

Access to businesses and residences to be maintained and open, however expect some changes and gravel surfaces. The road will be temporarily impassable at some locations to complete underground work, seek nearest alternative route. Get updates delivered to you inbox. Sign up for email updates.