Expect lane closures/delays on Highway 210 in Baxter
Traffic Impacts
July 20 - Crews have completed paving the Highway 210 mainline and turn lanes.
Motorists may continue to encounter periodic lane closures as crews complete permanent road markings and work at/on Timberwood Drive.
BAXTER, Minn. - The Minnesota Department of Transportation and the city of Baxter are partnering to construct a $1.2 million road and safety improvement project on Highway 210 in Baxter that began Monday, June 28.
Work that began June 28
Access improvements will be constructed at the intersection of Highway 210 and the new city street to be named Timberwood Drive just east of the Cass County line. Work includes a new left turn lane and overhead intersection lighting on Highway 210 and completing construction of Timberwood Drive. Motorists may encounter periodic lane/shoulder closures with flaggers controlling traffic.
Work that began July 12
Crews will resurface the Highway 210 mainline, including turn lanes, from Cass County line to Golf Course Road in Baxter. Motorists may encounter lane closures/shifts and flaggers controlling traffic at accesses.
Anderson Brothers Construction of Brainerd is the prime contractor for the project that is to be completed by July 29, weather permitting.
Motorists are asked to slow down, watch for crews working and heavy moving equipment. For updated statewide traffic, construction, weather and travel information visit www.511mn.org.