Traffic signal and lighting installations begin in
Crow Wing, Stearns, Todd, Wright counties

ST. CLOUD, Minn. - Motorists may encounter intermittent lane closures at the intersection of Highway 25 and Wright County Road 138 in Buffalo beginning Thursday, April 15 while crews install new traffic signals. The work should take approximately three weeks to complete.

On Monday, April 19, crews will begin installing new signals at the intersection of Highway 10 and 210 in Motley. This work is expected to be completed by mid-May.

  • UPDATE (May 24, 2010): The traffic signal system at the intersection of Hwy 10/Hwy 210 in Motley is scheduled to be operational on May 26.

Lighting installations are scheduled concurrently for various locations on Highway 371 in Crow Wing County, Highway 25 in Wright County, Highway 23 in Stearns County and Highway 55 in Wright County. This work is expected to be completed by early June. Lighting intersections at night in rural areas improves safety by helping motorists see they are approaching an intersection, according to the Minnesota Department of Transportation.

Motorists should slow down and watch for intermittent lanes closures in areas where crews are working.

Design Electric Inc. of St. Cloud is the prime contractor for this $340, 770 safety improvement project.