Washington Memorial Drive to 4th Avenue;
Overpass at Lake George
Beginning Monday, July 6, the prime contractor will be closing
9th/10th Avenue each week night at 6:00 p.m. to do bridge demolition,
sheeting installation and 1st Street underground utility work.
The roadway will re-open to traffic at 6:00 a.m., daily. The City
of St. Cloud has waived the noise ordinance to allow crews to
complete this work. This work is expected to be completed by Friday,
July 10, weather permitting.
In addition, on Monday, July 6, the contractor will be closing
the 14th Avenue intersection on the south side of Highway 23.
It will remain closed until work on the eastbound lanes is completed.
This closure is required to do intersection work.
Mississippi River Bridge
Crews continue to erect bridge beams and girders. The remaining
beams and girders will be set from the west abutment to Pier #1
and begin setting girders for the final Span 2.
Crews will begin removing the old concrete roadway on the west
side after the west abutment girders are set.
Crews continue working on walls for the bike trail on the west
side of the river.
Granite stone veneer installation continues on the west abutment.
Retaining wall on the west side of the river is being removed.
Construction will begin on the new wall after girders are set
for the west abutment.
The Desoto Monument has been removed and will be delivered to
the city of St. Cloud for restoration and future placement.
Boat traffic will be maintained on the Mississippi River during
this project.
Existing local and truck detours will remain in place.
Project Updates
News and detour information: http://www.dot.state.mn.us/d3/projects/hwy23bridge/
To subscribe to e-mail updates for the Highway 23 Improvement
Project in St. Cloud, visit www.mndot.gov.