Two
separate work zones will be contained within a two-mile stretch
of roadway to allow crews to place anchors and follow-up with
socket installation.
H&R Construction Company of Dalton is the prime contractor
for the $1.4 million safety improvement project, funded by
the American
Recovery and Reinvestment Act, signed into law Feb. 17,
2009.
In 2009, central Minnesota will have 70 miles of safety median
cable guardrail installed along I-94, with future plans to
install the remaining 30 miles by early 2011.
For updated statewide traffic, construction, weather and
travel information, visit www.511mn.org.
|