| Location: |
Six-mile stretch of northbound and southbound Highway 169
north of Elk River
|
| Timeframe: |
Beginning Wednesday,
Aug. 20, for approximately two weeks. Crews will work each day,
Monday through Thursday, from 9 a.m. to 4:30 p.m. |
| Traffic
Impact: |
Single-lane closures with delays. Motorists should pay attention
for signs, workers and moving equipment in the work zone.
|
Project
Information: |
Crews will repair potholes in the roadway surface.
For updated statewide traffic, construction, weather and
travel information, visit www.511mn.org
|