Hwy 25 improvements

South of I-94 in Monticello

Reconstruct, expand to four lanes

Hwy25 Improvements mapTraffic impacts through August

Highway 25 from south of School Blvd to south of CR 106/85th St NE

  • Traffic shifted onto temporary narrowed lanes through the work zone
  • Also possible lane closures, access closures, flaggers and detours

Cone graphic photo
Pay attention and watch for workers, equipment, traffic devices and signs

Schedule*

  Reconstruct northbound Now -June
  Reconstruct southbound July-August
  Resurface August -Sept

*Schedule subject to change

Summary of work

Reconstruct south of the MHP entrances to CR 106/85th St NE

  • Expand to four lanes
  • Improve pedestrian accessibility
  • Improve drainage
  • Install a new traffic signal with a flashing yellow arrow, turn lanes and LED overhead lights at the intersection of Hwy 25 and CR 106/85th St NE

Resurface south of I-94 to south of the MHP entrances

  • Upgrade traffic signals at Oakwood Dr, Chelsea Rd and School Blvd
  • Install new sidewalk west of Hwy 25 from MHP to School Blvd

Cost

  • $5.7 million