MnDOT Contacts
- Dan Labo
Project Engineer
320-223-6605 - JP Gillach
Communications
218-828-5706
Location
- Wright CR 18/39 in Monticello to the Crow River in St. Michael
Schedule
- Late May – Early August 2013
Cost
-
$8.4 million
2013 Construction
Repair ten miles of westbound I-94, and 1.5 miles of eastbound I-94, from Monticello to St. Michael in summer 2013. Crews will rehabilitate concrete pavement, resurface ramps and shoulders, and make other needed improvements.
Traffic Impacts
I-94 will be intermittently reduced to a single lane during non-rush hours late May - July 2013.
-
Expect reduced speeds, lane shifts and occasional overnight ramp closures
-
Road segments may be temporarily bumpier than normal
-
Check 511 for real-time lane closures, traffic cams and speeds
-
Do the Zipper Merge when you encounter congested traffic
In the Surrounding Area
- I-94 Clearwater to St. Cloud, single lane two-way traffic, delays, reduced speeds, April - July 2013
- I-694 Arden Hills to Brooklyn Center, lane closures, delays, reduced speeds, June – November 2013

Detailed map
Benefits
Preserve and provide a smoother ride on 10 miles of heavily used interstate that carries up to 70,000 vehicles per day on average, including high volumes of commercial, commuter and weekend traffic.
-
Quieter ride and extended road service life of 10-12 years while reducing short-term maintenance costs
- Resurface shoulders and ramps at Hwy 241, Wright CR 19 and Wright CR 37
- Make other repairs under required closures to minimize any future inconveniences