Minnesota Department of Transportation

511 Travel Info

Hwy 65—Isanti County

Cambridge to south of Isanti at Anoka County line

Resurface, improve

Segments of lane closures on both directions of Highway 65 until early-June, 2018. Project map

Traffic impacts

Edgewood, Isanti, East Bethel

  • Both directions of Hwy 65 to have segments of single-lane closures, during non-rush hours, Mon-Sat on good weather days, with reduced speeds and lane shifts.
  • Check 511mn.org for today's road conditions and travel speeds.

Project work

Now to early-June

  • Paving is complete. Crews will install permanent striping and rumble strips, repair/line drainage pipes, and wrap up this two-year project in June.
  • Project schedule


For your safety and ours, please watch for crews, equipment and slow or stopped traffic.

When complete in early-June, 2018, the two-year project will resurface the roadway, extend turn lanes, repair or replace drainage, resurface the Hwy 65/Hwy 95 interchange ramps in Cambridge, make intersection improvements, upgrade signal systems and improve pedestrian accessibility. More about this project

Schedule

Hwy 65 Dates Traffic Impact Work
Cambridge/Edgewood - 357th Ave NE to CR 19/305th Ave COMPLETE: July 24 to Sept 11, 2017 Single-lane traffic on southbound

Resurface northbound

Cambridge/Edgewood - 357th Ave NE to CR 19/305th Ave COMPLETE: Sept 11 to Nov. 7, 2017 Single lane traffic on northbound Resurface southbound
Work operations suspend for 2017-2018 winter season
Edgewood to south of Isanti - CR 19/305th Ave to 245th Ave NE at the Anoka/Isanti county line March 26-early-June, 2018 Segments of single-lane traffic on both directions Resurface northbound and southbound

Information tentative and subject to change.