Hwy 10 Elk River–Lake Orono Bridge

Replace bridge, improve road surface

Reconstruct, improve

Today on Highway 10

Good news–Crews have completed major construction on Hwy 10 for 2017. Both eastbound lanes of Hwy 10 and accesses at 185th Ave/Joplin St opened Thursday, Oct. 26. You may encounter some lane or shoulder closures, as crews wrap-up the season. MnDOT thanks you for your patience during this first year of construction. For current travel speeds and road conditions, check 511mn.org

Project map

Schedule

Hwy 10 Elk River Dates Traffic Impact Work
Lake Orono Bridge to east of Waco St/185th Ave NW July 24 to Aug. 30, 2017

All lanes of traffic on westbound side - EB one lane, WB two lanes

COMPLETE: Reconstruct eastbound
Lake Orono Bridge to east of Waco St/185th Ave NW Aug. 30 to mid-Oct 2017

All lanes of traffic on eastbound side - EB one lane, WB two lanes

COMPLETE: Reconstruct westbound
Xenia Ave NW to east of Waco St/185th Ave NW Oct. 2 to Oct 26, 2017

W of Lake Orono Bridge to Waco St: EB one lane on new EB side, WB two lanes on new WB side

E of Lake Orono Bridge to Xenia Ave:

Lane closures on both directions

COMPLETE: Complete 2017 work and remove temp lanes; construct 2018 temp crossovers; prepare bridge site

Oct. 26 to mid-Nov. Periodic lane closures to finish work/clean-up and relocate utilities. Map
Work operations suspend for 2017-2018 winter season
East of Joplin St/185th Ave NW to Xenia Ave NW April to Oct, 2018

All lanes of traffic on either side of roadway - EB one lane, WB two lanes

Reconstruct lanes, Lake Orono bridge

Schedule TBD

Lake Orono waterway

Open

Elk River is Open for Business

Access to local businesses and residences to be maintained and open, follow directional signs.