Hwy 2 and Hwy 197 Resurfacing

Bemidji

Project information

Project Update

(July 6, 2017)

With the Fourth of July holiday in our rearview mirror, motorists will see some changes to the area’s construction projects. Work on the Highway 2 Bypass will transition from the stage 1 detour to stage 2 beginning tomorrow (July 7) when crews remove the detour on the Hwy 71 southbound bridge.

The Hwy 197/Bemidji Ave resurfacing project is scheduled to kick off on Monday, July 10. Residents and business owners are invited to take part in today’s open house from 3 - 5 p.m. at the Tourist Information Center.

Upcoming Schedule

Hwy 2- Bypass

  • Friday, July 7- Stage 1 detour removed from the Hwy 71 southbound bridge.
  • Friday, July 7- Begin stage 2 detour of the westbound Hwy 2 bridge near the airport. Motorists will use the Hwy 71 exit to Paul Bunyan drive and turn west at the light to access Hwy 2.
  • Traffic control switch on the Hwy 2 lane crossovers.

Hwy 197/Bemidji Ave- Downtown (Begins July 10)

  • Thursday, July 6- Open house from 3-5 p.m. at the Tourist Information Building.
  • Monday, July 10- Construction begins.
  • Crews will begin with the outside lane (lakeside) of the northbound lanes. When complete, work will shift to the inside lane.
  • Only 1 of the 4 lanes will be closed at any one time.
  • Motorists can expect traffic backups during peak travel times.
  • The City of Bemidji recently approved the installation of a signalized crosswalk across the northbound lanes. It will be located near the Dairy Queen at Cross St SW.
Hwy 2 and Hwy 197 project information
Highway 2 staged detours

Summary of work

Hwy 2- Bypass

  • Schedule: May 15 - Sept
  • Resurface between Moberg Drive and 1/2 mile west of Hubbard County Line (Airport to Animal Land)
  • Repair bridges

Hwy 197- Downtown

  • Schedule: July 10 - Sept
  • Resurface between 3rd St NW to 7th St SE (Paul and Babe to Lueken's South)
  • Sidewalk, crosswalk and pedestrian access improvements
  • Storm sewer replacement

Traffic impacts

Hwy 2- Bypass

  • Alternating detour for the bridges on the north side of the bypass
    • Hwy 71 southbound bridge connection to the bypass (near Manard's)
      • Detour south on Highway 197 through Bemidji
    • Hwy 2 northbound bridge connection to westbound Highway 2 (near airport)
      • Detour onto Hwy 71 exit, then west onto Highway 2
  • Lane closures

Hwy 197- Downtown

  • Lane closures- (project will begin with the lakeside lanes)

Cost Estimate

Hwy 2- Bypass

  • $5.35 million

Hwy 197- Downtown

  • $2 million