Local traffic can once again have access at the intersection of Highway 75 and Main Street in Hendrum. Paving is currently underway in Halstad. Crews continue to install storm sewer in Hendrum. Access to local businesses and residents will be maintained throughout the project. Access to the Back Forty Bar and Offsale, as well as Fredrick-Ganje Funeral Home, will be maintained from Hwy 75 by use of the frontage road, south of Halstad.

(Updated September 6, 2019)

See below for detour maps and information in Halstad and Hendrum

Public Meetings

  • Tuesdays, 10:00 a.m.
    • Halstad- (September 10, 24) at the Legion Recreation Center, 580 Second Avenue West
    • Hendrum- (September 17) a the Civic Center/Fire Hall, 308 Main Street East
  • See maps below for detour staging in Halstad and Hendrum

 

Current Traffic impacts

  • The overall detour for motorists traveling Hwy 75 is
    • Halstad- County Roads 10, 19 and 21
    • Hendrum- County Roads 4, 25, 39
  • See maps below for detour staging in Halstad and Hendrum

Summary of Project

  • Urban reconstruct
  • Raise the highway grade
  • Concrete resurfacing
  • Construct turn Lanes
  • Install highway lighting
  • Replace sidewalks
  • Pedestrian accessibility improvements
  • Culvert replacement
  • Replace storm sewer, curb and Gutter

Halstad

Highway 75 construction phasing in Halstad
Hwy 75- Halstad construction phasing
Highway 75 project in Hendrum
Hwy 75- streetscaping in Halstad

Detour Staging

  • Construction is split into phases
  • Each phase is done independently and in order.
  • Local access will be maintained for homes/businesses located within the workzone

Streetscaping

  • Decorative highway lighting
  • Stamped concrete

Hendrum

Highway 75 project in Halstad
Hwy 75- Hendrum construction phasing
Highway 75 project in Hendrum
Hwy 75- streetscaping in Hendrum

Detour staging

  • Construction is split into 3 phases
  • Each phase is done independently and in order.
  • Local access will be maintained for homes/businesses located within the workzone

Streetscaping

  • Decorative highway lighting
  • Stamped concrete