Hwy 2

Erskine

Traffic impacts

Project Update

  • Highway 2 is two-lane, two way traffic near the Highway 59 overpass. Both eastbound and westbound ramps are open. (Updated August 16, 2019)

 

Highway 2 project detour
Highway 2 project detour

2019 traffic impacts

  • Staged detours of Hwy 59 overpass bridges/ramps
  • Lane closures
  • Highway 2 lane crossovers

Hwy 59

Traveling south:
  • To westbound Hwy 2- detour onto CR 41 and CR 34
  • To eastbound Hwy 2 - ramp is open
Traveling north:
  • To westbound Hwy 2 - detour onto CR 41 CR 34
  • To eastbound Hwy 2 - ramp is open

Hwy 2

Traveling east
  • To northbound 59 - ramp is open
  • To southbound 59 - ramp is open
Traveling west
  • To northbound 59 - detour onto CR 41 in Mcintosh
  • To southbound 59 - detour onto CR 41 in Mcintosh

About this project

Highway 2 project limits
Highway 2 project construction limits

Summary of work

Most of the work for the Highway 2 reconstruction project, from Erskine to Highway 59, will take place during the 2019 construction. The project includes:

  • Reconstruction/replacement of the concrete pavement on Hwy 2 between west city limits in Erskine to the Oak Lake rest area.
  • Concrete bridge repairs and maintenance of Hwy 59 overpass bridges
  • Replacement of curb, gutter, storm sewer and culverts

Temporary crossovers were built in Fall 2018 to prepare for 2019 construction. That work has been completed.