Project information

Resurface Hwy 92 between south of the railroad tracks to Bagley High School.
UPDATE: Majority of the work south of Third Street is substantially complete and the project will resume in 2019 to complete Stages 2 and 3. This includes completing the multi-use pedestrian trail, concrete sidewalk, curb and gutter, and concrete boulevard, as well as final paving and turf work.
Summary of work
- Replace pavement and sidewalks
- New trail on east side by Bagley Park
- New trail and sidewalk on west side between high school and downtown
- Ugraded pedestrian accessibility and crossings
- Replace traffic signal at intersection of Hwy 2/92
- Upgrade/replace city utilities
- Map- Detailed look along the project limits
Project staging
COMPLETED: Stage 1A- Main Ave South
- Begins May 14 (approximately 6-7 weeks)
- Hwy 92 from the Hwy 2 intersection south to the softball fields
- Great Northern Drive SE (behind the fire station)
- Detour map- Stage 1A

COMPLETED: Stage 1B- Hwy 2/92 intersection
- Begins after stage 1A is complete (lasts 2 weeks)
- Intersection will be closed for 2 weeks
- Detour map- Stage 1B
RESUMES IN 2019: Stage 2- Main Ave North
- Done concurrently with Stage 3:
- Between Hwy 2 and Fourth Street N
- No two consecutive crossovers can be closed at the same time
- Detour map- Stage 2
RESUMES IN 2019: Stage 3- Main Ave North
- Done concurrently with Stage 2:
- Between Fourth Street N and Seventh Street N
- Detour map- Stage 3
COMPLETED: Stage 4- Hwy 92 near Bagley High School
- Done concurrently with Stage 1A
- From Seveth Street N to past Bagley High School
- Detour will last up to 3 weeks
- Detour map- Stage 4