D2 ATP Information
Counties covered by MnDOT District 2:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
![]() |
|
Schedule of activities
September-January
Solicit projects for four fiscal years in the next STIP plus one additional planning year
January-March
Select projects, provide a public comment period on projects
April 15
Draft ATP due to the Office of Capital Programs and Performance Measurement
May 1
OCPPM prepares draft STIP, sends to District ATP
May-June
Review and comment on STIP, due July 1
July-August
OCPPM develops final draft STIP
August-October
MnDOT approves STIP and sends to FHWA/FTA for review
October-November
STIP approved by FHWA/FTA