I-35 Snake River bridge replacement project

In Pine County

Traffic impact

  • Southbound I-35 between the Pine County line and Hwy 7 has opened to two lanes of traffic, however motorists will still encounter some short, single-lane sections, Mondays through Fridays until October 28.
  • Northbound I-35 between the Pine County line and Hwy 7 is open to two lanes of traffic, however motorists will still encounter some short, single-lane sections, Mondays through Fridays until October 28.
  • Southbound and northbound I-35 between the Pine County line and Hwy 7will be open to both lanes, with no single lane sections on weekends.
  • Traffic over the Snake River (approximately one mile) will remain in two-lane, two way configuration on the northbound side. The southbound bridge is still under construction and is expected reopen about October 28.

April 2019 – October 2019
Planned Hwy 70 and County Road 7 bridge replacements

 


There is another project on I-35 in the Twin Cities Metro Area.
For complete details about this project please visit the project website.

I-35 project map

Overview map of the projects on I-35 between Duluth and Pine City

Help us get the word out

MnDOT wants to be sure that as many people as possible are aware of this project and potential traffic delays. Please feel free to print this poster and post at your place of business or at other places where people will see it. Thanks you!

About this project

Summary of work

  • Construct four new bridges at the Snake River, Hwy 70 and County Road 7
  • Seven miles of resurfacing using unbonded concrete overlay

I-35 Snake River Construction Schedule
April 2018 – October 2018
First stage: Construct seven miles of northbound I-35 pavement and the northbound I-35 Snake River Bridge.
Second stage: Construct seven miles of southbound I-35 pavement and the southbound I-35 Snake River Bridge.