Summary of work

  • Mile marker 18 to 25 (south of Cromwell) resurfacing
  • Mile marker 31.3 to 33.6 (north of Cromwell) resurfacing
  • Mile marker 43.1 to 43.7 (Floodwood) resurfacing and accessibility improvements
  • Mile marker 48 to 69.6 (north of Floodwood) resurfacing
Project Improvements
In Floodwood
  • New curb and gutter and sidewalk
  • Upgraded curb ramps on Highway 2
  • 2-inch mill and 2-inch overlay
  • North of Floodwood River, road width reduced and parking removed
  • Minor city utility work—sanitary sewer

Rural Segments

  • Six culvert replacements
  • South of Cromwell—3-inch mill and 3-inch bituminous overlay
  • North of Cromwell—Rural segment 1.5-inch mill and 3-inch overlay including shoulders