Rural Work: Two Harbors to Silver Creek Tunnel including Campground Road

Traffic impacts

  • There will be no traffic impacts until the permanent signals are installed.
  • Temporary signals are in operation until the materials needed for the permanent signals arrive.

Contacts for traffic control and road maintenance:
                Eddy Simons (Holden):  218-591-8508
                Heath Line (KGM):  218-780-9267
                Jessie Johnson (Holden):  218-851-2033

 

 

A rendering of the Hwy 61 Two Harbors project.

A rendering of the Hwy 61 Two Harbors project.

About this project

Summary of work

  • Signal replacements on Hwy 61 in Two Harbors
  • New turn lanes
  • Resurfacing
  • Sidewalk and accessibility improvements
  • Urban storm sewer work
  • Rural culvert work
  • New Municipal Campground entrance at Campground Road

Meetings

A public open house was held July 23, 2018 in Two Harbors at the Two Harbors Public Building, Law Enforcement Center. The meeting provided updated information for citizens and business owners about the upcoming “urban” phase of the project.

A public open house was held May 16, 2018 in Two Harbors at the Two Harbors Public Building, Law Enforcement Center. Proposed layouts were on display during the open house.

A public open house was held February 7, 2017 in Two Harbors. Approximately 50 people attended. Proposed layouts were on display during the open house.

A public open house was held Tuesday, March 7, 2016 at the Two Harbors Community Building, 417 South Avenue from 6 p.m. to 9 p.m. Project layouts and other displays were available while staff answered questions and took comments.