Relocation of Hwy 53
Between Eveleth and Virginia
Project Home | Project Schedule | Alternatives & External Studies | Documents | FAQs | Contacts

Project schedule

 

The 1960 highway easement provided for three years from the notice of termination of easement rights to when the highway must be relocated. MnDOT requested that this be amended to a minimum of seven years.

 

Project Scedule
Draft EIS February 2013
Draft EIS Public Hearing Spring 2013
Identification of Preferred Alternative Spring 2013
Final EIS Early 2014
Record of Decision Fall 2014
Detail Design Spring 2014 to Winter 2015
Right of Way Acquisition Early 2014 to Spring 2015
Contract Letting Spring 2015
Open to Traffic Fall 2016
Removal of Easement May 5, 2017