Relocation of Hwy 53
Between Eveleth and Virginia
Project Home | Project Schedule | Alternatives & External Studies | Documents | FAQs | Contacts

Tentative project schedule

 

The 1960 highway easement provided for three years from the notice of termination of easement rights to when the highway must be relocated. MnDOT requested that this be amended to a minimum of seven years.

 

Tentative Project Schedule (subject to change)
Conduct Additional Studies April 2013 – Spring 2014
Community and Agency Meetings 2013 – 2014
Amended Scoping Decision Document (SDD)

Spring/Summer 2013

Draft EIS Publication

Summer 2014

Select Preferred Alternative

Fall/Winter 2014.

Final EIS

Spring 2015

Record of Decision Summer 2015
Construction Late 2015 – Spring 2017