Hwy 53 from Virginia to Cook
Four-lane expansion improvement project
Location
- From Virginia to the south limits of Cook
Schedule
- Oct. 2012 to Aug. 2015
Project Description
Hwy 53 will be expanded to four-lanes from Virginia to the south limits of Cook. It will be built in two stages with a total length of approximately 20 miles. The first stage from approximately County Road 307 to 0.25 miles south of County Road 652 (Goodell Road) was completed in 2009. Construction on the second stage is scheduled to begin in Oct. 2012.
- Project background (PDF 15 KB)
Hwy 53 Virginia to Cook - Environmental process (PDF 24 KB)
Traffic impacts
- No current traffic impacts
Benefits
- Improved traffic flow and safety