Hwy 37

St. Louis County

This project is substantially complete

Work on this project is completed for 2017. Work will resume in spring 2018 to complete the remaining pavement markings.

Hwy 37 project map
Hwy 37 project map.

Traffic impacts

None currently, however, watch for the tapered bump. Signs mark the location (about two miles east of Hibbing).

Summary of work

  • Resurfacing Hwy 37 from 0.29 miles east of Hwy 169 to Hwy 53 in St. Louis County

Project update November 7

An extremely wet fall, followed by early snow and freezing temperatures have prevented completion of this project.

Work on the project will resume in spring 2018. The permanent pavement is down on all but two miles on the Hibbing side of the project. Motorists will see signs that mark the location of a tapered bump where the unfinished section is located.

The remaining two-mile section will be paved in the spring and then the new pavement markings will be applied..

Thank you for your patience during this project.