Hwy 169 Cross-Range Expressway


About this project

Graphic showing areas where the improvements to Hwy 169 will be made.

Oct. 11 Project Update

Work has been temporarily suspended on this project due to an unforeseen soil stability issue. Work is expected to resume sometime after October 31.

All project signage and traffic control will remain in place during the work suspension.

Correcting the soil issue requires a revised work plan. Once this is completed, work will resume.

This brief delay is not expected to affect the fall 2017 project completion date.

Work is expected to wrap-up for 2016 in late-November

Traffic impacts

Brief, intermittent closures

Most of the work on this project will not affect traffic. When traffic is affected, motorists may encounter brief, intermittent, temporary closures controlled by flaggers.

Hwy 169 with orange cones directing traffic. The area beside the highway has been graded and has hay scatterred on top of the soil.

Hwy 169 project site.


Summary of work

  • Expand 1.55 miles of Hwy 169 from two- to four-lanes as part of the Corridors of Commerce Program
  • Install intersection lighting
  • Replace box culvert


  • Survey Mapping, Soil Investigations - May 2014
  • Environmental Assessment (Re-Evaluation) - Fall 2014
  • Right of Way Acquisition Complete - Spring 2016
  • Final Design - Start July 2014 and finish spring 2016
  • Project Letting - June 2016

Project layout

Click on layout for a larger view:

Icon map showing location of Phase II of the Cross-Range Expressway.