Traffic impacts

Brief, intermittent closures

Most of the work on this project will not affect traffic. When traffic is affected, motorists may encounter brief, intermittent, temporary closures controlled by flaggers.

Summary of work

  • Expand 1.55 miles of Hwy 169 from two- to four-lanes as part of the Corridors of Commerce Program
  • Install intersection lighting
  • Replace box culvert

Timeline

  • Survey Mapping, Soil Investigations - May 2014
  • Environmental Assessment (Re-Evaluation) - Fall 2014
  • Right of Way Acquisition Complete - Spring 2016
  • Final Design - Start July 2014 and finish spring 2016
  • Project Letting - June 2016

Project layout

Click on layout for a larger view:

Icon map showing location of Phase II of the Cross-Range Expressway.