Minnesota Department of Transportation

511 Travel Info

2019 Construction Kickoff

State road construction projects

Lists updated 4 p.m., April 4, 2019

View Excel spreadsheet version

Route SP Public Description Starting Const. Date Ending Const. Date  Est. CY 2019 Expenditures
(based on curves) 
Hwy 65 0112-52 Resurface Hwy 65 from just south of Sandy River to just south of Hwy 200 in Aitkin County
5/27/2019 8/30/2019                         5,100,000.00
Hwy 23 0901-62 Remove SOO Line Railroad Bridge on Hwy 23, 10.7 miles north of the Carlton County line 5/20/2019 7/7/2019                             399,000.00
Hwy 23 0901-70 Replace the Hwy 23 bridge at Deer River 9.5 miles northeast of the south Carlton County line
9/16/2019 10/30/2020                         2,516,000.00
Hwy 65 3111-30 Resurface Hwy 65 from just south of Hwy 200 to Hwy 169 in Aitkin/Itasca counties
7/8/2019 10/18/2019                         7,418,000.00
Hwy 65 3112-37 Resurface Hwy 65 from Hwy 169 to Hawkins Ave in Nashwaulk 5/4/2018 6/28/2019                               94,000.00
Hwy 6 3603-14 Resurface Hwy 6 between Hwy 1 and Hwy 71 in Koochiching County
3/18/2019 8/16/2019                         5,822,000.00
Hwy 11 3606-61 Replace the bridge over the CN Railroad tracks on Hwy 11 just east of CR 20 in Rainier 1/26/2018 10/30/2019                         1,120,000.00
Hwy 61 3805-105 Repair retaining wall, resurface trails and parking lot at Gooseberry Falls rest area located off of Hwy 61
5/22/2019 11/30/2019                         1,500,000.00
Hwy 61 3805-107 Resurface Hwy 61 from Crow Creek to the Gooseberry River 8/1/2018 5/31/2019
I-35 5880-194 Replace the bridges at Hwy 70 and CR 7 over I-35 near Pine City 4/9/2018 10/31/2019                         3,342,000.00
Hwy 135 6912-77 Repair bridge and resurface Hwy 135 from Hwy 53 to the bridge over the Embarrass River near Embarrass
5/13/2019 9/28/2019                         7,508,000.00
Hwy 53 6917-143 Repair bridge and resurface Hwy 53 from just north of the Pale Face River to S Moon Lake Drive, improve accessibility at Anchor Lake rest area
6/10/2019 10/31/2019                         5,000,000.00
Hwy 53 6917-144 Replace the Hwy 37 Bridge over Hwy 53 south of Eveleth 4/6/2018 6/28/2019                             477,000.00
Hwy 53 6917-145 Resurface Hwy 53 between Hwy 37 and Eveleth, remove CN Railroad Bridge
11/3/2019 5/3/2020                         1,691,280.00
Hwy 53 6918-91 Landscape along Hwy 53 from Vermillion Dr to 2nd Ave in Virginia 2/12/2018 6/28/2019                               32,000.00
Hwy 53 6920-53 Install a Reduced Conflict Intersection and add 4 passing lanes from Angora to just north of Ray 7/10/2019 12/1/2019                         6,700,000.00
Hwy 73 6928-28 Resurface Hwy 73 in multiple locations from Cromwell to just south of Hibbing 7/29/2018 7/31/2019                         4,934,000.00
Hwy 73 6929-20 Reconstruct the Hwy 73 bridge over the BNSF Railroad in St. Louis County
7/15/2019 11/15/2019                         1,500,000.00
Hwy 194 6933-95 Repair pavement and ramps, improve accessibility, repair signals and storm sewers on Hwy 194 and Hwy 2 in Duluth 4/9/2018 6/28/2019                             420,000.00
Hwy 169 6935-89 Resurface through Mountain Iron and repair 2 bridges on Hwy 169 near Hwy 53 in Virginia  8/1/2017 9/30/2019                             215,000.00
Hwy 39 6941-08 Improve drainage and reconstruct Hwy 39 from Hwy 23 to the Oliver Bridge in Duluth
4/5/2019 8/12/2019                         1,811,000.00
6982-328 Resurface local streets and railroad crossings, improve intersections at Garfield Ave and Railroad St in Duluth 5/15/2019 11/30/2019                         2,000,000.00
Hwy 2  6982-334 Repair driving surfaces on Hwy 2 and I-35 in Proctor 5/15/2019 8/1/2019                             240,000.00
I-35 8821-254 Paint and repair 8 bridges on I-35 between Hinckley and Duluth 7/7/2018 7/31/2019                             603,000.00
8821-290 Drainage improvements to be determined
9/2/2019 11/30/2019                         1,500,000.00
8821-291 Drainage improvements to be determined
3/2/2019 11/30/2019                         1,209,000.00
8821-292 Pavement repairs districtwide
6/8/2018 12/31/2019                             155,000.00
8821-293 Pavement repairs districtwide
6/1/2019 9/1/2019                         1,812,000.00
8821-295 Install Rural Intersection Conflict Warning System at Hwy 65/Hwy 18 and Hwy 1/Hwy 73
9/3/2019 10/4/2019                             198,000.00
Hwy 61 8821-296 Replace signs on Hwy 61 from Duluth to Grand Marais
6/1/2019 9/1/2019                         1,100,000.00
8821-311 Improve safety on Hwy 2 and Hwy 61, install rumble strips at various locations
7/15/2019 11/30/2019                             140,000.00
 Hwy 23  6910-106 Hwy 23 in Duluth construct 134th Ave W 9/2/2019 11/30/2019                             200,000.00
32 Projects                      $66,756,000.00

Route SP Public Description Starting Const. Date Ending Const. Date  Est. CY 2019 Expenditures
(based on curves) 
Hwy 1 0404-38 Reconstruct Hwy 1 in Red Lake from Hwy 89 to 2.2 miles east of Hwy 89
7/1/2019 10/31/2019         4,150,000.00
Hwy 2 0406-62 Intersection and signal improvements at the Jct of Hwy 2 and Moberg Dr/Adams Ave in Bemidji
5/12/2019 9/12/2019             620,000.00
Hwy 71 0411-17 Reconstruct Hwy 71 from Blackduck to Hwy 1 5/1/2019 7/31/2019         4,926,000.00
Hwy 72 0412-27 Replace 3 culverts on Hwy 72 between Blackduck and Kelliher
9/3/2019 11/1/2019         2,500,000.00
Hwy 2 1120-56 Reconstruct Hwy 371 in Cass Lake; improve pedestrian accessibility and upgrade signal on Hwy 2

6/3/2019 10/31/2019         2,200,000.00
Hwy 92 1507-66 Reconstruct Hwy 92, improve pedestrian accessibility and construct bike/pedestrian trail in Bagley 5/20/2019 6/28/2019         5,400,000.00
Hwy 71 2904-15 Construct roundabout on Hwy 71 at CR 53/15 in Park Rapids
5/1/2019 10/31/2019         4,274,000.00
Hwy 71 2907-12 Replace culvert on Hwy 71 at Kabekona River 15 miles south of Bemidji 5/1/2019 6/28/2019             390,000.00
Hwy 1 3602-26 Reconstruct Hwy 1 in Northome; repave multi-use trail 7/8/2019 10/31/2019         2,700,000.00
Hwy 72 3903-30 Resurface 14 miles of Hwy 72 between CR 1 and south of the Beltrami County line 9/2/2019 10/31/2019         1,800,000.00
Hwy 72 3905-09 Replace Hwy 72 International Bridge over Rainy River in Baudette 5/1/2019 12/2/2019       39,400,000.00
Hwy 75 4507-53 Replace 3 culverts on Hwy 75 south of Donaldson
5/13/2019 7/26/2019         1,099,000.00
Hwy 220 4512-36 Replace bridges on Hwy 220 over the Snake and Tamarac rivers between Hwy 317 and Hwy 11
6/3/2019 9/12/2019         3,362,000.00
Hwy 32 5404-27 Replace culvert on Hwy 32 at Mashaug Creek north of Twin Valley
7/15/2019 9/6/2019         1,682,000.00
Hwy 75 5406-18 Reconstruct and flood mitigation on Hwy 75 in Hendrum
5/20/2019 10/5/2019         3,500,000.00
Hwy 75 5409-32 Reconstruct and flood mitigation on Hwy 75 in Hendrum
5/20/2019 10/5/2019         4,300,000.00
Hwy 9 5410-26 Resurface Hwy 9 between Ada and the Clay County line 8/19/2019 9/27/2019         1,400,000.00
Hwy 2 6004-24 Concrete resurface, replace culverts and improve drainage on Hwy 2 between Erskine and Hwy 59; repair 2 bridges on Hwy 59 over Hwy 2 5/1/2019 10/31/2019       12,300,000.00
Hwy 32 6016-43 Repaint bridges on Hwy 220 in Climax and on Hwy 32 in Red Lake Falls
9/9/2019 10/31/2019             609,000.00
Hwy 197 8822-215 Replace lighting from CR 11 to Beltrami/Hubbard County line and on Hwy 197, replace signals at the intersection of 3rd St & Mall entrance 5/1/2019 5/31/2019             824,000.00
20 Projects               $97,436,000.00

Route SP Public Description Starting Const. Date Ending Const. Date  Est. CY 2019 Expenditures
(based on curves) 
Hwy 18 0102-25 Replace bridge spanning Morman Creek near Mille Lacs Lake 6/15/2019 8/15/2019         1,615,000.00
Hwy 169 0115-51 Restore historic Pine-Hickory Lakes roadside parking area 6/15/2019 8/15/2019             730,000.00
Hwy 6 1802-53 Resurface 14 miles, pave gravel shoulders south of Emily, add right-turn lanes at Smokey Hollow Rd and Fletcher Rd, replace/repair pipes and guardrail, replace sidewalk connecting Roosevelt Lake Bridge and public dock in Outing 7/9/2019 9/12/2019         3,350,000.00
Hwy 210 1806-76 Reconstruct 11 miles, replace/repair pipes (full-depth reclamation), reconstruct Hwy 210/CR 12 intersection, add turn lanes, bypass lanes, install rumble/mumble strips 6/17/2019 11/1/2019         6,900,000.00
Hwy 371 1810-108 Landcape 8/25/2018 7/15/2019             164,000.00
Hwy 371 1810-110 Landcape 8/25/2018 7/15/2019             116,000.00
Hwy 65 3003-47 Resurface SB lanes from Isanti/Anoka county line to end of 4 lane segment; and from Isanti CR 19/305th Ave. NE to end of 4 lane segment in Cambridge; and NB lane from one mile S of Isanti CR 5 in Isanti to end of 4 lane segment north of Cambridge
7/15/2018 7/15/2020               75,000.00
Hwy 65 3004-62 Install new Continuous Green-T intersection, extend turn lanes, widen shoulders 4/15/2019 6/1/2019         2,276,000.00
Hwy 169 4814-3355A Restore historic White Fish Creek bridge 4/15/2019 7/15/2019         1,856,000.00
Hwy 27 4904-45 Reconstruct from 6th St W to 2nd St E; add new curb, gutter, sidewalk, bike lane, railroad crossing; improve signals and underground utilities. Resurface 9th St SE to near 15th St SW; improve signals and pedestrian access 4/15/2019 10/1/2019         7,547,000.00
Hwy 4 7301-38 Reconstruct 21 miles of road surface (full-depth reclamation), repair/replace 40 pipes, remove three cattle passes, improve guardrail, install rumble/mumble strips 7/8/2019 10/11/2019         9,953,000.00
Hwy 15 7303-50 Reconstruct 12 miles (full-depth reclamation) from Hwy 55 in Kimball to 66th Ave in St. Augusta, replace or repair underground pipes and box culverts, add new mumble strips, improve accessibility and signal at Hwy 15/CR47/CR136 intersection in St. Augusta  2/11/2019 7/28/2019         8,726,000.00
Hwy 55 7314-39 Resurface 9 miles from W of Regal to Lake Ave in Paynesville, redeck bridge spanning railroad, upgrade guardrail, install rumble/mumble strips 7/8/2019 8/30/2019         3,310,000.00
I-94 7380-237 Add new loop ramp from WB I-94 to EB Hwy 23, new loop ramp from EB I-94 to WB Hwy 23, and new deceleration lanes along I-94  8/15/2019 10/15/2020         2,200,000.00
I-94 7380-246 Redeck/repair CR 159/St. John’s Rd/135th Ave bridge 4/15/2019 6/15/2019             890,000.00
I 94 7380-254 Expand commercial truck parking lot, resurface ramps, improve sidewalk, install new overhead LED lighting, improve accessibility 7/8/2019 8/30/2019         1,476,000.00
Hwy 10 8001-40 Reconstruct and redesign Hwy 10 through business district, resurface from 620th Ave to near Oink Joint Rd/140th St, replace signals at Hwy 10/Second St W and Hwy 10/Hwy 71, upgrade railroad crossing at Hwy 71 and Second St W, construct new left-turn lanes at Hwy 10/CR 75, replace underground utilities 4/15/2019 9/15/2019     12,348,000.00
Hwy 25 8604-42 Reconstruct 7 miles from Settlers Pkwy in Buffalo to Hwy 12 near Montrose, repair/replace 20 underground pipes/box culverts, upgrade guardrail, install mumble/rumble strips 8/5/2019 10/13/2019         6,177,000.00
Hwy 55 8606-60 Reconstruct 12 miles from Annandale Blvd in Annandale to Hwy 25 in Buffalo; add new center left-turn lane plus improve signal and pedestrian access in Maple Lake, repair/replace underground pipes, remove cattle passes 2/18/2019 7/27/2019       11,048,000.00
I-94 8680-172 Reconstruct and improve 6 miles from Hwy 241 to west of CR 19; add lanes, add new pavement, add ramps at interchanges, reconstruct bridges, upgrade signals and drainage systems, add new raised concrete center median barrier, build trails and sidewalk 6/1/2019 11/1/2021       47,819,000.00
I-94 8680-173 Reconstruct and improve 14 miles from west of Hwy 25 to Hwy 24; add lanes, add new pavement, new weigh-in-motion system, concrete center median barrier, construct noisewall in Monticello, improve drainage 8/1/2019 11/1/2021       59,508,000.00
  8823-336 Districtwide D3 aggregate shouldering 5/1/2019 11/1/2019             617,000.00
  8823-337 Districtwide aggregate shouldering 5/1/2019 11/1/2019             537,000.00
  8823-338 Districtwide reconstruction  5/1/2019 11/1/2019         4,087,000.00
  8823-339 Districtwide microsurfacing and sealcoat 5/1/2019 11/1/2019         3,725,000.00
  8823-340 Districtwide culvert lining 5/1/2019 11/1/2019             500,000.00
Hwy 371 8823-351 Hwy 371 sign replacement 7/8/2019 10/18/2019         1,200,000.00
27 Projects             $198,750,000.00

Route SP Public Description Starting Const. Date Ending Const. Date  Est. CY 2019 Expenditures
I-94 1480-177 Install weigh-in-motion scale  5/1/2019 7/1/2019                                 620,000.00
I-94 2180-115 Concrete resurface from Hwy 114 to Hwy 29, Garfield to Alexandria 5/1/2019 11/1/2019                             6,264,000.00
Hwy 59 2609-39 Complete streets reconstruction, lighting and pedestrian accessibility improvements in Elbow Lake 5/13/2019 8/13/2019                             2,617,000.00
Hwy 28 6103-34 Resurface and widen shoulders from Glenwood to Starbuck
5/1/2019 11/1/2019                             5,500,000.00
Hwy 75 7802-35 Resurface and replace sidewalks within city of Wheaton  5/1/2019 7/1/2019                             1,740,000.00
Hwy 75 8408-58 Resurface from Wolverton to Clay/Wilkin county line, includes pedestrian accessibility improvements and utility repairs within the city of Wolverton 3/22/2019 9/12/2019                             1,700,000.00
  8824-175 Districtwide seal coat project 5/1/2019 8/1/2019                             2,000,000.00
Hwy 119 7611-15M Resurface from Hwy 40 in Lac Qui Parle County to Hwy 12 near Appleton, excludes city limits of Appleton 5/1/2019 6/1/2019                             3,400,000.00
Hwy 55 2609-36 Resurface from Barrett to Douglas/Grant county line; replace Pomme de Terre River Bridge 7/1/2019 9/15/2019                             5,000,000.00
Hwy 10 8824-184 Districtwide chip seal project, westbound Hwy 10 east of Perham to Frazee 7/1/2019 10/1/2019                             4,000,000.00
10 Projects                           $32,841,000.00

Route SP Public Description Starting Const. Date Ending Const. Date  Est. CY 2019 Expenditures
  0202-110 Resurface and add parking space addition at Dayton Port weigh station in Ramsey 7/15/2019 8/30/2019                        433,000.00
Hwy 65 0207-105 Replace signs on Hwy 65 from Hennepin-Anoka County line to Hwy 10 in Blaine 4/15/2019 6/20/2019                        599,000.00
Hwy 65 0207-99 Replace signal system and improve pedestrian crossings on Hwy 65 at 41st Ave NE in Columbia Heights 9/3/2019 10/15/2019                        280,000.00
Hwy 65 0208-157 Construct reduced conflict intersections on Hwy 65 from Ham Lake to East Bethel at 143rd Ave NE, 153rd Ave NE, 157th Ave NE, 181st Ave NE, 187th Ave NE, and Viking Blvd
7/9/2018 8/30/2019                     6,500,000.00
I-35E 0282-40 Install fence on I-35E in Lino Lakes
7/1/2019 7/15/2020                        118,000.00
I-694 0285-67 Replace signal system on I-694 at the north and south ramps at East River Rd/Anoka CR 1 in Fridley 7/15/2019 9/15/2019                        500,000.00
Hwy 41 1008-92 Landscape on Hwy 41, 0.14 mile north of Hwy 212 to 0.3 miles north of Carver CR 14 in Chaska
4/1/2018 7/15/2019                           12,000.00
Hwy 212 1013-90 Repair drainage and construct reduced conflict intersection on Hwy 212 at Carver CR  41 in Benton Township and Carver CR 36 in Dahlgren Township
8/15/2019 10/1/2019                     1,141,000.00
Hwy 8 1308-26 Install 6" wet reflective striping on Hwy 8 from I-35 in Forest Lake to Minn/Wis state line
9/6/2019 10/30/2019                        540,000.00
I-35 1380-84 Resurface pavement, repair stormwater drainage  on I-35 from Chisago CR 9 to Chisago/Pine county line
3/30/2019 11/15/2019                  22,600,000.00
Hwy 10 1380-86 Replace lighting at Dayton Port rest area and Rush City rest area 3/30/2019 11/15/2019                        185,000.00
Hwy 52 1905-41 Resurface and install cable median barrier on  Hwy 52 from  Hwy 19 to 0.2 miles north of Dakota CR 86 in Randolph Township
9/7/2019 10/1/2020                        500,000.00
Hwy 50 1906-70 Expand park and car pool lot to provide parking at Hwy 50 in NW quadrant in Hampton
5/13/2019 7/20/2019                        200,000.00
Hwy 55 1910-50 Install traffic management system and improve signal timing on Hwy 55 from Hwy 61 to General Sieben Drive and Hwy 61 from Dakota CR 47 to 4th St in Hastings
9/3/2019 5/1/2020                        300,000.00
Hwy 149 1917-45 Mill and overlay, ADA, drainage, signals on Hwy 149 in Mendota Heights, West St Paul and St Paul 4/1/2019 6/20/2019                     2,000,000.00
Hwy  149 1917-51 Landscape on Hwy 149 from I-494 to Hwy 5 in St. Paul and Hwy 13 from Hwy 140 to Cherokee Heights Blvd
10/1/2019 6/1/2021                        109,000.00
Hwy 62 1918-118 Replace signal at Hwy 62 and Hwy 149 (Dodd Rd) in Mendota Heights 10/1/2018 5/15/2019                        300,000.00
Hwy 77 1925-56 Repair bridge and add sidewalk access improvements at Cliff Rd over Hwy 77 in Eagan
4/8/2019 7/2/2019                     2,212,000.00
I-35W 1981-124 Replace bridge on I-35W over Minnesota River from Black Dog Rd in Burnsville to 106th St in Bloomington including design-build activities 7/9/2019 9/15/2021                113,954,000.00
I-35W 1981-134 Construct high occupancy vehicle bypass, repair concrete pavement on I-35W from Burnsville Parkway to northbound I-35W in Burnsville
4/18/2019 6/7/2019                        665,000.00
I-494 1985-148 I-494 from Concord to Minnesota River, resurface and repair 7 bridges 7/10/2009 10/1/2020                  15,000,000.00
I-494 1985-149 Resurface, construct auxiliary lane, repair bridge and construct retaining wall and noise wall,  install lighting, signs and traffic management system, rebuild storm sewer and improve drainage on I-494 from Hardman Ave in South St. Paul to Blaine Ave 8/6/2018 10/1/2019                     5,706,000.00
Hwy 12 2713-117 Replace signs and panels on Hwy 12 from BNSF Railroad in Maple Plain to I-494/I-394 in Minnetonka
4/15/2019 6/6/2019                        567,000.00
Hwy 12 2714-145 Repair bridge, approach panels,signals; improve lighting and sidewalk accessibility on Hwy 12 at Central Ave in Wayzata
4/29/2019 10/25/2019                     4,017,000.00
Hwy 55 2722-84 Replace signs on Hwy 55 from Old Rockford Road/Hamel Rd in Plymouth to Mpls city limit
5/3/2019 6/28/2019                        495,000.00
Hwy 55 2723-140 Repair retaining wall on Hwy 55 at Hwy 100 4/15/2019 6/28/2019                        187,000.00
Hwy 55 2724-127 Repair storm tunnel at Hwy 55 to 29th St and 1.5 miles along 28th St E to Mississippi River in Mpls
12/7/2018 5/24/2019                        700,000.00
Hwy 169 2750-88 Reconstruct, replace 2 bridges and extend turn lane from Hayden Lake Rd to Dean Ave in Champlin
10/23/2018 2/15/2019                     3,209,000.00
Hwy 169 2750-95 Construct Hwy 169 bus shoulders - 63rd Ave. to Hwy 610 7/8/2019 11/1/2019                        952,000.00
Hwy212 2763-53 Replace sign on Hwy 212 from I-494 in Eden Prairie to Hwy 169/Hwy 62 in Edina
9/9/2019 11/15/2019                        250,000.00
Hwy 610 2771-109 Install snow fence/landscape along the Hwy 610 corridor in Brooklyn Park 8/13/2018 7/15/2019                           36,000.00
Hwy 62 2774-23 Repair bridge and construct acceleration lane at EB entrance ramp on Hwy 62 at France Ave in Edina 4/8/2019 8/9/2019                     3,915,000.00
I-94 2780-99 Widen I-94 and construct temporary crossovers 7/21/2019 11/1/2019                  11,400,000.00
I-94 2781-447 Repair 3 bridges on I-94 at entrance and exit ramps over LRT, at 17th Ave south; and at Hiawatha bicycle trl in Mpls
4/15/2019 10/1/2019                     1,800,000.00
I-94 2781-498 Install pile wraps for 2 piers on I-94 bridge EB and WB at Shingle Creek Pkwy
7/29/2019 10/15/2019                        300,000.00
I-35W 2782-327 Construct MnPASS lane; reconstruct road; construct transit station, noise walls, retaining walls and build 6 bridges; replace 13 bridges, and repair 3 bridges on I-35W in Mpls from 43rd St to 11th Ave; on I-94 from 1st Ave to Park Ave; and on Hwy 65 from 24th St to 15th St    8/7/2017 10/22/2021                  35,937,000.00
I 35W 2782-330 Resurface, repair drainage and pipe, improve pedestrian ramps and install traffic management system on I-35W from Portland Ave to Washington Ave; and on Hwy 65 from 15th St to 10th St in Mpls 7/8/2019 10/1/2019                     2,273,000.00
I-35W 2782-347 Construct stormwater holding cavern system on I-35W from 42nd St to 39th St in Mpls 8/1/2019 7/1/2022                     5,000,000.00
I-35W 2782-350 Replace MnPASS signs on I-35/I-35W from 150th St (Burnsville) to 42nd St Mpls 9/10/2019 6/21/2019                           71,000.00
I-35W 2783-148 Replace pedestrian bridge and approaches at 5th St SE in Mpls and improve sidewalk  4/1/2019 8/17/2019                     3,562,000.00
I-494 2785-419 Landscape on I-494 from I-394 in Minnetonka to the I-94/I-694 interchange in Maple Grove 9/10/2018 7/15/2019                        157,000.00
I-494 2785-426 Landscape from I-494 from I-394 in Minnetonka to I-94/I-494 in Maple Grove 9/10/2018 7/15/2019                        138,000.00
I-394 2789-151 I-394 repair bridges  8/1/2019 7/15/2020  
Hwy 10 6205-39 Construct a third EB lane on Hwy 10 between I-35W and Co Rd. 96; build a two-lane exit from SB I-35W to EB Hwy 10 and noise walls in Arden Hills  4/15/2019 9/6/2019                     2,900,000.00
Hwy 51 6215-106 Replace signal system on Hwy 51 (Snelling Ave) at Midway Pkwy/Dan Patch Avenue in St. Paul 9/12/2019 11/15/2019                        435,000.00
Hwy 51 6216-136 Replace signal system at Hoyt Ave in Falcon Heights, St. Paul 5/13/2019 7/12/2019                        386,000.00
Hwy 61 6220-83 Replace lighting on Hwy 61 from Maxwell Ave in Maplewood to 0.1 miles north of Warner Rd in St. Paul 7/8/2019 10/4/2019                        921,000.00
Hwy 149 6223-20 High Bridge Hwy 149 re-decking project in St Paul 9/6/2018 6/1/2019                     1,000,000.00
Hwy 120 6227-83 Install traffic management system and improve signal timing on Hwy 120 from I-94 ramp to Woodland Drive in Maplewood 5/6/2019 9/8/2019                        550,000.00
I-35E 6280-406 Landscape on I-35E from 7th St W to Grand Ave in St Paul 7/27/2019 1/27/2020                           45,000.00
I-94 6282-212 Resurface, control erosion and repair drainage on I-94 from Hwy 280 to 0.1 mile west of Western Ave in St. Paul 5/3/2019 11/3/2019                     8,685,000.00
Hwy 10 6284-180 Construct MnPASS lane, resurface, repair 17 bridges, replace 5 bridges. Project on I-35W is from CR B-2 in Roseville to 0.1 mile north of Sunset Avenue in Lino Lakes; on Hwy 10  from  I-35W to 0.7 miles east of CR ?? 4/1/2019 9/2/2021                  95,000,000.00
I-694 6285-157 Landscape on I-694 from Rice St in Little Canada to Lexington Ave in Arden Hills
4/7/2019 7/15/2019                        125,000.00
Hwy 13 7001-115 Resurface, install concrete median, repair drainage and add turn lanes from Hwy 19 in Cedar Lake Township to 0.1 miles south of Eagle Creek Ave in Prior Lake 5/13/2019 10/11/2019                     7,782,000.00
Hwy 21 7002-47 Resurface, add turn lanes on Hwy 21, and  improve sidewalk accessibility and drainage from Hwy 19 in New Prague to Hwy 169 in Jordan 3/15/2019 7/2/2019                     4,814,000.00
Hwy 95 8208-40 Construct turn lanes, widen shoulders and resurface Hwy 95 from 70th St to Hwy 61 in Cottage Grove
6/10/2019 10/1/2020                     6,491,000.00
Hwy 36 8214-176 Landscape on Hwy 36 from Sunnyside Dr to 0.2 mile N of Sunnyside Dr 5/1/2019 7/15/2019                        246,000.00
  8217-34 Convert Stillwater Lift Bridge into bicycle and pedestrian crossing 8/7/2017 7/15/2019                     4,000,000.00
I-35 8280-47 Resurface 6 miles of existing pavement from I-35W/I-35E split to Hwy 8; replace Hwy 97 Bridge with diverging diamond interchange and replace two other bridges 8/1/2017 11/1/2019                  30,000,000.00
I-94 8282-128 Reconstruct bike trail and repair drainage on the north side of I-94 along Manning Ave, from Hudson Blvd to 450 ft north of Hudson Blvd

4/15/2019 6/15/2019                           90,000.00
  8282-137 Construct I-94 bike path 4/29/2019 7/13/2019                        734,000.00
I-94 8286-81 Resurface, repair 4 bridges on I-694, reconstruct ramp from 0.1 mile south of 10th St in Oakdale to 0.1 mile south of Tamarack Rd in Woodbury
12/10/2018 11/30/2020                  15,000,000.00
  8825-558 Districtwide pond restoration  10/22/2018 5/24/2019                        500,000.00
  8825-579 Districtwide highfriction seal 7/15/2019 7/31/2019                        840,000.00
  8825-599 Districtwide preventative maintenance seal coating, microsurface, fog seal at various locations   5/5/2018 6/9/2020  
  8825-608 Replace traffic detector loops districtwide
11/12/2018 5/12/202                             7,000.00
  8825-609 Replace traffic detector loop districtwide
11/12/2018 5/12/2020                             7,000.00
  8825-658 Installing dynamic message signs districtwide  9/10/2018 6/21/2018                        865,000.00
  8825-659 Repair noise walls districtwide 11/10/2018 6/1/2019                     3,000,000.00
  8825-665 RestripingI-394, 62, Park, Portland  4/15/2018 6/1/2022 $150,000
  8825-673 Replace cameras and shelters districtwide
8/5/2019 11/15/2019                     1,210,000.00
  8825-679 Districtwide mill and overlay preventative maintenance 5/14/2018 11/7/2020                                          -  
  8825-682 Overhead sign replacement districtwide
7/15/2019 10/19/2019                     2,000,000.00
  8825-705 Bridge deck flood seal districtwide 8/6/2018 12/31/2020                             5,500.00
  8825-751 Districtwide concrete pavement repair 7/15/2019 10/1/2021                        498,000.00
  8825-753 Districtwide resurfacing 5/1/2019 2/22/2022                     6,795,000.00
76 Projects         $443,901,500.00

Route SP Public Description Starting Const. Date Ending Const. Date  Est. CY 2019 Expenditures
Hwy 14 2002-33 Repave Hwy 14 EB 1.5 miles E of Dodge CR 9 to 1.1 miles E of Hwy 57, including EB ramps and Hwy 56 from 0.35 mi N of CR 10 to Jct Hwy 14 and from Jct WB Hwy 14 to CR 34 9/23/2019 10/14/2019                      2,000,000.00
Hwy 14 2001-42 Expand Hwy 14 to 4 lanes between Owatonna and Dodge Center 10/1/2019 10/1/2021                      2,000,000.00
Hwy 57 2007-41 Reconstruct Hwy 57 Bridge No. 6862 over N Branch Middle Fork Zumbro River, Bridge No. 6861 Over Milliken Creek and Bridge No. 6867 Over Mid Fork Zumbro River 4/1/2019 10/1/2019                             4,063,000.00
Hwy 30 2305-29 Repave Hwy 30 from Hwy 74 to W city limits at Rushford  8/19/2019 10/14/2019                      5,000,000.00
I-90 2482-74 Repave I-90 WB lanes from Hwy 13 to Freeborn CR 46 at Petran and redeck Bridge No. 9727
5/1/2019 9/1/2019                    17,215,000.00
I-90 2482-78 Reconstruct and expand I-90 Oakland Woods rest area parking lot 5/27/2019 10/30/2020                      2,174,000.00
I-90 2482-79 Reconstruct and expand I-90 Hayward rest area parking lot 5/27/2019 10/30/2020                      1,993,000.00
Hwy 52 2505-57 Install Hwy 52 Traffic Management System Olmsted CR 12/112 (Elk Run) to Hwy 60 W at Zumbrota 4/5/2019 10/5/2019                                 738,000.00
Hwy 63 2515-21 Hwy 63 Red Wing Bridge replacement  5/5/2017 8/20/2020                           18,500,000.00
Hwy 16 5003-17 Repave Hwy 16 and improve pedestrian accessibility I-90 to Tracy Rd In Spring Valley and replace bridge Nos. 6045, 6046 and 6047 5/8/2019 9/8/2019                             5,529,000.00
Hwy 218 5008-35 Construct Hwy 218 SB bypass lane and NB right turn lane at Pershing Ave in Lyle 9/16/2019 10/7/2019                         300,000.00
Hwy 52 5507-64 Repave Hwy 52 and make pedestrian improvements from Fillmore CR 5 in Chatfield to I-90 and replace Bridge Nos. 6124, 8182 and 8183 5/6/2019 9/13/2019                             7,900,000.00
Hwy 63 5509-86 Install cable median barrier on Hwy 63 in Stewartville to Hwy 52
3/8/2019 9/8/2019                                 920,000.00
Hwy 60 6607-50 Reconstruct and improve pedestrian accessibility on Hwy 60 In Faribault from Hwy 21 to Central Ave  5/1/2019 9/1/2019                             6,300,000.00
I-35 6680-116 Reconstruct I-35 Heath Creek rest area parking lot 5/27/2019 10/30/2020                             2,537,000.00
I-35 7480-131 Reconstruct I-35 Straight River rest area parking lot 5/27/2019 10/30/2020                             1,903,000.00
I-35 7480-132 Install Hwy 35 roadway lighting at the NB and SB Ramps at Steele CR 9  9/23/2019 10/14/2019                                 250,000.00
Hwy 60 7903-54 Repave Hwy 60 from Hwy 63 Zumbro Falls to Hwy 61 near Wabasha

5/20/2019 9/20/2019                           10,900,000.00
Hwy 61 7906-96 Repave Hwy 61 and improve pedestrian accessibility on Hwy 42 to 1 mile N of Lake City; excluding Lake City for future project 5/30/2019 9/30/2019                           11,100,000.00
Hwy 74 7909-04 Replace Hwy 74 Bridge No. 8355  7/29/2019 8/23/2019                                 174,000.00
Hwy 43  8503-5900E WP #5 Rehabilitate Hwy 43 Winona Bridge (CARRY-OVER) 9/26/2016 6/30/2019                             1,986,000.00
Hwy 61 8504-79 Repave Hwy 61 N of I-90 to Winona CR 15 at Homer
5/6/2019 9/27/2019                             9,700,000.00
I-90 8580-167 Repave WB I-90 near Hwy 61/Dakota to W of WB entrance ramp from Hwy 61 NB, EB I-90 near Hwy 61/Dakota to W of S limits of Dakota and Hwy 61 from N I-90 to 0.4 miles N of I-90 8/5/2019 10/11/2019                             4,407,000.00
I-90 8580-172 Repair I-90 Bridge Nos. 85817, 85818, 85823, 85824, 85829, 85830, 85841, 85842, 85843, 85844, 85845, 85846 5/1/2019 7/1/2019                             6,400,000.00
  8826-193 Districtwide seal coat, various locations  6/30/2019 7/8/2019                             2,347,000.00
  8826-197 Districtwide epoxy bridge deck crack seal, various locations 5/13/2019 6/20/2019                             1,042,000.00
  8826-213 Districtwide culvert linings 9/10/2019 11/1/2019                                 750,000.00
  8826-215 Districtwide concrete pavement restoration  6/1/2019 11/1/2019                             3,990,000.00
28 Projects                           $132,118,000.00

Route SP Public Description Starting Const. Date Ending Const. Date  Est. CY 2019 Expenditures
Hwy 22 0704-110 Landscape Hwy 22 Mapleton (including plaza area) to Mankato 8/13/2018 7/1/2019                                 762,000.00
Hwy 14 0804-81 Replace bridges over Minnesota River and DME railroad, improve pedestrian access in New Ulm, and construct a new interchange at intersection of Hwy 15 /CR 21
4/12/2018 10/16/2019                           10,580,000.00
Hwy 60 1703-73 Resurface Hwy 62 to 490th Ave in Windom
5/20/2019 7/26/2019                             3,247,000.00
Hwy 60 3204-72 Install reduced conflict intersection (J-turn) on Hwy 60 at Jackson CR 24 6/1/2019 10/1/2019                             3,445,000.00
Hwy 99 4010-10 Resurface, widen and replace Minnesota River bridge in St Peter to CR 38 and from Hwy 13 to Hwy 21 in Le Sueur County
5/1/2019 10/1/2019                                 8,200,000.00
Hwy 4 4601-32 Resurface Iowa State line to Martin CR 26 and replace 2 bridges
4/15/2019 8/30/2019                             3,750,000.00
I-90 4680-129 Resurface I-90 Hwy 15 to 2 miles west of Hwy 169 and repair multiple bridges 3/11/2019 10/17/2019                           38,541,000.00
Hwy 91 5308-29 Resurface and replace 2 culverts S Adrian limits to Nobles/Murray County line and improve pedestrian crossings in Adrian
8/5/2019 7/3/2020                             8,193,000.00
Hwy 60 8309-52 Repair and resurface 1 mile west of Hwy 4 to Hwy 15
6/18/2018 10/25/2019                           12,830,000.00
Hwy 19 4004-132 Stabilize slope around bridge, 1 mile E of Henderson 10/1/2019 11/15/2019                                 200,000.00
  8827-298 Districtwide repair culverts on various roadways 7/15/2019 10/15/2019                                 150,000.00
  8827-299 Districtwide resurface bridge surfaces 7/15/2019 10/15/2019                                 250,000.00
  8827-301 Districtwide resurface roads 7/15/2019 10/15/2019                                 250,000.00
  8827-304 Districtwide resurface roads 5/15/2019 10/31/2019                                 500,000.00
I-90 8827-314 Install lighting at rural intersections along I-90 8/19/2019 9/16/2019                                 400,000.00
  8827-315 Districtwide replace signs  4/22/2019 5/13/2019                                 114,000.00
  8827-316 Districtwide repair signals and lighting at various locations 6/24/2019 8/17/2019                                 110,000.00
17 Projects                                   $91,522,000.00

Route SP Public Description Starting Const. Date Ending Const. Date  Est. CY 2019 Expenditures
Hwy 40 1209-22 Replace bridge on Hwy 40 (known as Milan bridge) over Lac qui Parle Lake west of Milan 4/1/2019 7/1/2019                 5,300,000.00
Hwy 12 3403-74 Realign Hwy 12 and reconstruct Hwy 40 including 2 new bridges to facilitate a railroad bypass on the west side of Willmar 5/6/2019 11/15/2020               25,195,000.00
Hwy 5 4109-29 Resurface Hwy 75 from Ivanhoe to Canby, upgrade sidewalks in Canby 8/5/2019 9/16/2019                 3,422,000.00
Hwy 23 4207-57 Construct Reduced Conflict Intersection, or J-turn, at the intersection of Hwy 23 and Lyon CR 7 in Marshall 4/29/2019 7/19/2019                 1,200,000.00
Hwy 4 4702-12 Resurface Hwy 4 from the east jct of Hwy 12 to Hwy 55 6/1/2019 11/1/2019                 1,700,000.00
Hwy 22 4704-89 Reconstruct 4th St in Litchfield from Hwy 12 to N Donnelly Ave
6/15/2019 9/30/2019                 8,800,000.00
Hwy 91 5107-14 Resurface Hwy 91 from the Murray/Nobles County line to Russell, replace bridges and repair culverts along project route, and upgrade sidewalks in Lake Wilson 7/15/2019 10/7/2020                 3,524,000.00
Hwy 91 5108-12 Resurface Hwy 91 from Lake Wilson to Hwy 23.  Replace bridge over ditch. 7/15/2019 10/7/2020                 6,700,000.00
Hwy 14 6401-37 Resurface pavement on Hwy 14 from 4th St in Tracy to CR 7 near Revere, repair culverts and guardrails along project route, extend right-turn lane at CR 80, upgrade sidewalks, ramps and adjacent driveways in Walnut Grove 4/15/2019 6/28/2019                 3,300,000.00
Hwy 119 7611-15 Resurface Hwy 119 from Hwy 40 to Hwy 12 5/13/2019 6/24/2019                 1,600,000.00
Hwy 67 8707-92 Replace two bridges over Boiling Spring Creek 1 mile north of Echo on Hwy 67 7/8/2019 8/5/2019                     505,000.00
Hwy 68 8708-12 Replace bridge over Lazarus Creek, 3 miles west of Canby  on Hwy 68 8/5/2019 10/28/2019                     940,000.00
12 Projects                 $62,186,000.00