Construction Tools - Contract Changes
Methods used to modify construction contracts
Home | Innovative Contracting | Contractor Payments | Contract Changes | Project Controls | Labor Compliance | References | Contacts

Claims

Claims submittals

Contacts

Contract changes

 

Design-bid-build forms

Change Order
Work Order/MEW

 

Supplemental Agreement

Standard
Part A
Part B

 

Sample Language

Change Order
Work Order/MEW
Supplemental Agreement

 

Design-build forms

Standard
Part A
Part B

 

Design-Build Partnering Sample Language
(to add professional partnering facilitator for project already let)

CO level 2 Part A
CO level 2 Part B

 

Design Build Partnering Sample Language

Part A

Part B

 

IDIQ

 

 

Sample Language - Work Orders

 

Work Order Language
Download the desired sample and paste it onto a Work Order form

 

Replace the underlined phrases and question marks with the appropriate information

 

Situation Reason to Use Minor Extra Work
Basic Standard work order language for minor extra work.
Item omitted from Plan Plan failed to address work needed to complete Project as intended.
Changed condition Minor extra work needed because of conditions are different than those indicated in Plan.
Minor design change

Change Plan design. NOTE:  Does not include mainline road above grade, bridges, or anything over $50,000.