The 35W@94 Downtown to Crosstown project will be completed in five stages:

Stage 1: Summer 2017 to Summer 2018 (PDF)

  • Portland Ave. and Franklin Ave. Bridges closing
  • 38th St. Bridge closing
  • WB I-94 to 11th St. ramp closing
  • 5th Ave. ramps closing (5th Ave. to NB I-35W ramp will close for the remainder of the project)
  • 36th St. to SB I-35W ramp will close for the remainder of the project
  • Local road work with closures will begin

Stage 2: Summer 2018 to Fall 2018 (PDF)

  • 26th St. Bridge closing
  • 24th St. Ped Bridge closing (will be closed for the remainder of the project)
  • 40th St. Ped Bridge closing
  • Access ramps to/from downtown will be closing
  • I-35W and I-94 Interchange closing for the remainder of the project
  • 31st St. ramps closing (except to emergency vehicles and transit; 31st St. to SB I-35W ramp closed for the remainder of the project)
  • 35th St. ramps closing (35th St to NB I-35W ramp closed for the remainder of the project)
  • I-35W and I-94 lane reductions begin
  • Local road work with closures continues
  • View all construction activities for summer 2018 (PDF)

Stage 3: Fall 2018 to Summer 2019 (PDF)

  • 28th St. Bridge closing
  • NB I-35W to Downtown (11th St/Grant St) access ramp will have lane reductions for the remainder of the project
  • Downtown (12th St/4th Ave) to SB I-35W access ramp closing (except to emergency vehicles and transit)
  • 31st St. to SB I-35W ramp closed to ALL traffic for the remainder of the project
  • I-35W and I-94 lane reductions continue
  • Local road work with lane reductions and closures begin

Stage 4: Summer 2019 to Fall 2020 (PDF)

  • SB I-35W to 46th St. ramp closing
  • I-35W and I-94 lane reductions continue
  • Local road work with lane reductions and closures continues

Stage 5: Fall 2020 to Fall 2021 (PDF)

  • NB I-35W to 31st St ramp closing for the remainder of the project
  • NB I-35W to 36th St ramp closing for the remainder of the project
  • I-35W and I-94 lane reductions continue
  • Local road work with lane reductions and closures continues